← all projects
🚆Transportstrategic

Cross-city rail tunnel in Łódź (Łódź Fabryczna – Łódź Kaliska/Żabieniec)

pausedstage: constructionover budget
2.3 bn PLN
estimate · data from Feb 2025net or gross: not recorded≈ 2.3 bn PLN (value-by-stage, est., nominal)

An underground railway tunnel connecting the Łódź Fabryczna station with Łódź Kaliska and Łódź Żabieniec: a double-track section 3 km long and four single-track tunnels with a total length of 4.5 km, with new underground stops in the city center. The tender was announced in November 2016, the contract with the PBDiM consortium from Mińsk Mazowiecki (PLN 1.59 billion) was signed at the end of 2017, and boring began in 2019. After a tenement house above the route of the TBM machine collapsed in September 2024, boring was suspended – the shield has remained immobilized since November 2024. In February 2026, PKP PLK withdrew from the contract with the contractor; the selection of a new one is underway (a tender at the turn of Q3 and Q4 2026). The cost grew from approx. PLN 1.3 billion net to approx. PLN 2.3 billion, and completion was pushed back from 2022 to the turn of 2030 and 2031.

How it went

Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one has an assessment with no confirmed quote. How to read this section

No source calls this a delay and the card makes no assessment here, but the dates recorded on this project differ by 9 years: originally 2022, currently 2031.

Deliverypartial[3]
Budgetover budget[2]
Utilisationnot operational[3]
Lossesknown sunk cost[8]

Timeline

  1. Announced28 Nov 2016
  2. Construction start2019
  3. Original date2022
  4. Current date2031

Change history

  • 2019stage: construction
  • 28 Nov 2016stage: tender

Significance

The tunnel is intended to enable railway traffic through the center of Łódź: beyond the Łódź Fabryczna station the route splits north to the Łódź Żabieniec station and south to the Łódź Kaliska station, and new underground stops are being built in the city center (including at the junction of Zielona, Zachodnia and Kościuszki streets and at Ogrodowa, Karskiego and Drewnowska streets). The investment transforms Łódź Fabryczna from a terminal station into a through station, tying together the Łódź railway junction.

Sources 11 · 7 independent · 10 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. PKP Polskie Linie Kolejowe S.A.28 Nov 2016
    AnnouncedOriginal dateInvestorStage history
    Announced · Investor · Stage historyPKP Polskie Linie Kolejowe S.A. ogłosiły przetarg na budowę tunelu łączącego Łódź Fabryczną z Łodzią Kaliską i Łodzią Żabieńcem.
    Original datePrace projektowe i budowlane zaplanowane są w latach 2017 – 2022.
    Locationtunel rozdzieli się na dwa kierunki: na północ doprowadzi do stacji Łódź Żabieniec, a na południe do stacji Łódź Kaliska.
  2. Money.pl25 Feb 2025
    CostBudget
    Cost2,3 mld zł
    Budgetobecnie realny koszt tej inwestycji to nie jest 1,3 mld zł netto, tylko 2,3 mld zł
  3. XYZ.pl11 Feb 2026
    StatusStageConstruction startStage historyUtilisationDelivery
    Status · UtilisationOd listopada 2024 r. tarcza pozostaje całkowicie unieruchomiona.
    Stage · Construction start · Stage historyDrążenie tunelu rozpoczęło się w 2019 r.
    DeliveryPierwotnie drążenie obiektu miało zakończyć się w czerwcu 2026 r.
  4. Rynek Infrastruktury27 May 2026
    Current date
    Current dateNa dzisiaj, zgodnie z harmonogramem, który mamy i który realizujemy w Polskich Liniach Kolejowych to jest przełom roku 2030 i 2031
  5. WNP.pl13 May 2026
    Status
    StatusZapewniamy, że inwestycja będzie kontynuowana, a wszystkie obecne działania mają jeden nadrzędny cel: jak najszybciej i w pełni bezpiecznie wznowić drążenie tunelu
  6. PortalSamorzadowy.pl5 Feb 2026
    Losses
    Lossesinwestując w projekt własne środki - ponad pół miliarda złotych
  7. Radio Łódź2 Mar 2026
    Losses
    LossesZostaliśmy bez głównego największego dla nas kontraktu z obciążeniami, z długami, z należnościami
  8. Expressilustrowany.pl / eGlos5 Feb 2026
    Losses
    LossesPKP PLK były zmuszone uregulować wobec podwykonawców należności sięgające łącznie około ćwierć miliarda złotych.
  9. Funding
    FundingTunel średnicowy w Łodzi może - a raczej mógł - liczyć na unijne dofinansowanie rzędu 411 mln euro, czyli nawet 1,8 mld zł
  10. Funding
    FundingUbytek ten zostanie wyrównany środkami krajowymi (zapewne wraz z kolejnym zwiększeniem kwoty kontraktu). – Tunel w Łodzi przechodzi na finansowanie z budżetu państwa – podkreślił wiceminister.