Tunnel under the Świna in Świnoujście

completed stage: operational delivereddelayed
914 mln PLN
programme budget (multi-year) · data from 30 Jun 2023 ≈ 914 mln PLN (value-by-stage, est., nominal) funding: EU POIiŚ 2014–2020: PLN 775.6 million (85%), City of Świnoujście budget

A road tunnel under the Świna strait, connecting the islands of Uznam and Wolin in Świnoujście — the city's first fixed road connection with the rest of the country, replacing the previous ferry crossings. The section bored by a TBM machine is nearly 1,500 m long. The investor was the City of Świnoujście with the support of GDDKiA; the total value of the investment amounted to PLN 913.8 million, with EU co-financing of PLN 775.6 million from the Operational Programme Infrastructure and Environment (POIiŚ). Work began in the autumn of 2019, and the tunnel was opened to traffic on 30 June 2023 — about a year later than the originally announced autumn of 2022.

How it went

Assessment: settled. Signals only where documented.

Delivery delivered
Schedule delayed
Budget on budget
Utilisation in use
Scope as announced

Timeline

Slip: +9 mo. vs. the original date

  1. Construction start 2019
  2. Original date 2022
  3. Delivery 30 Jun 2023

Change history

  • 30 Jun 2023 stage: operational
  • 2019 stage: construction

Significance

The tunnel eliminated Świnoujście's dependence on ferry crossings as the only connection of the left-bank part of the city (the island of Uznam) with the rest of the country — the drive through the tunnel takes about two minutes. The crossing is heavily used: in the three years since its opening (up to June 2026), more than 15.1 million journeys were recorded, and 2025 was a record year with more than 5.2 million vehicles.

Sources 5 · 2 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. Ministerstwo Infrastruktury (gov.pl) 30 Jun 2023
    CostStatusDeliveryInvestorOutcome
    Cost „Łączna szacowana wartość inwestycji to 913,8 mln zł."
    Delivery „30 czerwca 2023 r. w godzinach wieczornych pierwsi kierowcy przejadą tunelem"
    Scope „Odcinek drążony maszyną TBM ma blisko 1500 m długości"
  2. GDDKiA (gov.pl) 30 Jun 2023
    Construction startInvestorStatus
    Construction start „jesienią 2019 roku ruszyły pierwsze prace"
    Investor „GDDKiA w imieniu Miasta Świnoujście uzyskała decyzję środowiskową"
  3. Wikipedia (pl)
    Original datecost.fundingOutcome
    cost.funding „775,6 mln zł"
    Original date „tunel miał być gotowy jesienią 2022"
    locations „53°53′39,00″N 14°15′18,99″E/53,894167 14,255275"
    Schedule „Zgodnie z umową z wykonawcą, tunel miał być gotowy jesienią 2022."
    Budget „757,7 miliona złotych netto i 932 miliony złotych brutto ... Łączna szacowana wartość inwestycji to 913,8 mln zł."
  4. Miasto Świnoujście (swinoujscie.pl) Jun 2026
    StatusStageOutcomeUtilisation
    Status „30 czerwca 2023 roku oficjalnie otwarto tunel"
    Stage „15 149 440 pojazdów"
    Delivery „30 czerwca 2023 roku oficjalnie otwarto tunel pod Świną"
  5. iSwinoujscie.pl Jan 2026
    Utilisation
    Utilisation „Od stycznia do grudnia tunelem przejechało 5 252 490 pojazdów, a średnia dobowa wzrosła do 14 390. Rekordowym miesiącem był sierpień – 585 681 przejazdów, co oznaczało blisko 18,9 tys. pojazdów dziennie."