T5 Terminal at the Port of Gdańsk – offshore wind installation terminal
A new T5 terminal being built on an area of approx. 21 ha reclaimed from the sea in the Baltic Hub area at the Port of Gdańsk, carried out on behalf of the company Istrana (85% owned by the Polish Development Fund, 15% by Baltic Hub). In the first years of operation, the terminal is to serve as an installation base for offshore wind farms in the Baltic Sea. The facility will be equipped with two deepwater quays (451 m on the north-western side and 349 m on the northern side). The entire 21.3 ha terminal was leased by the company Elektrownia Wiatrowa Baltica 2, owned by PGE and Ørsted, for the installation of the Baltica 2 offshore wind farm. The cost of the investment is approx. PLN 1.18 billion, of which over PLN 900 million is funding from the National Recovery Plan. In April 2026 the progress of the reinforced concrete works was 85%, and completion of construction was planned for the third quarter of 2026.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section
Timeline
- Current dateSep 2026
Change history
- Apr 2026stage: construction
Significance
The T5 terminal is intended to become Poland's key installation base for offshore wind energy in the Baltic Sea. The entire facility was leased by the company Baltica 2 (PGE and Ørsted) for the construction of the Baltica 2 farm with a capacity of approx. 1.5 GW, making T5 a staging base for the assembly of offshore turbines from a Polish port. The investment physically expands the area of the Port of Gdańsk by more than 21 ha of land reclaimed from the sea and strengthens Gdańsk's role in the supply chain for offshore projects on the Polish coast.
Sources 4 · 4 independent · 3 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- [1]Terminal T5 w Baltic Hub coraz bliżej obsługi offshore. Budowa wchodzi w kluczową fazę ↗archived ✓Polski Portal Morski (polskamorska.pl)30 Apr 2026StatusStageStage historyProgressCurrent dateFunding
Status · Current dateZgodnie z wcześniejszym harmonogramem zakończenie budowy terminala T5 planowane jest na trzeci kwartał 2026 roku.
The source gives the third quarter of 2026; the card reads a period as its last month (a date given as a period means its end).
Stage · Stage history · ProgressAktualnie znajdujemy się w szczytowej fazie robót żelbetowych, a ich zaawansowanie wynosi 85%.
LocationTerminal T5 w Baltic Hub coraz bliżej obsługi offshore.
FundingProjekt współfinansowany jest ze środków europejskich w ramach Krajowego Planu Odbudowy oraz przez Polski Fundusz Rozwoju.
- [2]Terminal T5 znalazł dzierżawców z branży OZE – umowa PGE, Ørsted, Istrana, Baltic Hub ↗archived ✓gdansk.plInvestor
InvestorJej właścicielami jest w 85% rządowy Polski Fundusz Rozwoju oraz w 15% Baltic Hub w Gdańsku
- investmap.plCostFunding
CostZmniejszenie odległości terminali od miejsca realizacji inwestycji morskich farm wiatrowych pozwoli nie tylko obniżyć koszty, jak również wpłynie na zapewnienie terminowości realizacji inwestycji. Koszt całkowity przedsięwzięcia w Gdańsku to prawie 1,18 mld zł, w tym dofinansowanie unijne ponad 0,9 mld zł.
FundingInwestycja otrzyma ponad 900 mln zł dofinansowania z Krajowego Planu Odbudowy i Zwiększania Odporności (KPO).
- IntermodalNews10 Jul 2026