T5 Terminal at the Port of Gdańsk — offshore wind installation terminal
A new T5 terminal being built on an area of approx. 21 ha reclaimed from the sea in the Baltic Hub area at the Port of Gdańsk, carried out on behalf of the company Istrana (85% owned by the Polish Development Fund, 15% by Baltic Hub). In the first years of operation, the terminal is to serve as an installation base for offshore wind farms in the Baltic Sea. The facility will be equipped with two deepwater quays (451 m on the north-western side and 349 m on the northern side). The entire 21.3 ha terminal was leased by the company Elektrownia Wiatrowa Baltica 2, owned by PGE and Ørsted, for the installation of the Baltica 2 offshore wind farm. The cost of the investment is approx. PLN 1.18 billion, of which over PLN 900 million is funding from the National Recovery Plan. In April 2026 the progress of the reinforced concrete works was 85%, and completion of construction was planned for the third quarter of 2026.
How it went
Assessment: too early to assess. Signals only where documented.
Timeline
- Current date Sep 2026
Change history
- Apr 2026 stage: construction
Significance
The T5 terminal is intended to become Poland's key installation base for offshore wind energy in the Baltic Sea. The entire facility was leased by the company Baltica 2 (PGE and Ørsted) for the construction of the Baltica 2 farm with a capacity of approx. 1.5 GW, making T5 a staging base for the assembly of offshore turbines from a Polish port. The investment physically expands the area of the Port of Gdańsk by more than 21 ha of land reclaimed from the sea and strengthens Gdańsk's role in the supply chain for offshore projects on the Polish coast.
Sources 4 · 3 archived
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- Polski Portal Morski (polskamorska.pl) 30 Apr 2026StatusStageStage historyprogress.pctCurrent date
Status „Zgodnie z wcześniejszym harmonogramem zakończenie budowy terminala T5 planowane jest na trzeci kwartał 2026 roku."
Stage „Aktualnie znajdujemy się w szczytowej fazie robót żelbetowych, a ich zaawansowanie wynosi 85%."
locations.0.voivodeship „Terminal T5 w Baltic Hub coraz bliżej obsługi offshore."
- gdansk.plInvestor
Investor „Jej właścicielami jest w 85% rządowy Polski Fundusz Rozwoju oraz w 15% Baltic Hub w Gdańsku"
- investmap.plCost
Cost „Samo T5 kosztuje prawie 1,18 miliarda złotych, z czego ponad 900 milionów złotych to dofinansowanie unijne z Krajowego Planu Odbudowy."
- IntermodalNews 10 Jul 2026Status