ORLEN Maritime Transshipment Terminal on the Martwa Wisła at the Gdańsk Refinery

completedstage: operational
PLN 500 million
programme budget (multi-year) · data from 2025net or gross: not recorded≈ PLN 500 million (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A new maritime transshipment terminal of the ORLEN Group built on the quay of the Martwa Wisła, directly at the Gdańsk Refinery (Pomorskie Voivodeship). The facility comprises an approx. 380-metre quay with two berths equipped with eight automated, bidirectional loading arms and a pipeline system connecting the terminal with the refinery's installations. The terminal can accommodate vessels up to 130 m in length. The target handling capacity is to reach up to 2 million tonnes of products per year – biocomponents for fuel production (including ethanol, MTBE, ETBE, FAME/UCOME), base oils, low-sulphur marine fuel (MGO), and refinery intermediates. Construction was carried out by a consortium led by the Sopot-based NDI Group. Work began in 2023, with the terminal originally expected to be commissioned in 2025. After construction was completed in 2026, commissioning and trial calls were carried out, including in May 2026, and the first commercial transshipment was performed on 15 July 2026, handling the tanker ECOMAL II.

How it went

No outcome assessment: this record carries none on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.

Timeline

  1. Construction start2023
  2. Original date2025
  3. Last stated date2026
  4. Delivery2026

Change history

  • Jul 2026stage: operational
  • 2026stage: commissioning
  • 2023stage: construction

Significance

The terminal is intended to be the maritime "export window" of the Gdańsk Refinery – it enables the direct loading and unloading of products by water, without the intermediation of a rail terminal, relieving the refinery's land logistics. It increases supply security through its own channel for importing biocomponents and components essential to fuel production, and for exporting petroleum products and base oils. The target throughput of around 2 million tonnes per year and the handling of low-sulphur marine fuel (MGO) strengthen Gdańsk's position in maritime fuel logistics and support biofuel production within the ORLEN Group.

Sources 8 · 7 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. money.pl2023
    CostOriginal date
    CostDodatkowo PKN Orlen zbuduje za 0,5 mld zł w terminal przeładunkowy
    Original dateNowy terminal na nabrzeżu Rafinerii Gdańskiej ma ruszyć w 2025 r.
  2. gdansk.plJan 2025
    Locationna Martwej Wiśle
  3. trojmiasto.pl2026
    Last stated date
    Last stated dateStart operacyjny zaplanowano na połowę 2026 r.
  4. money.pl2025
    Construction start
    Construction startInformując o postępie robót przy budowie terminala przeładunkowego na Martwej Wiśle, Orlen przypomniał, że inwestycja rozpoczęła się w styczniu 2023 r.
  5. gospodarkamorska.pl22 Jul 2026
    InvestorStatusStageStage historyDelivery
    InvestorPierwszy przeładunek komercyjny w terminalu Martwa Wisła. Projekt Grupy ORLEN działa
    Status · Stage · Stage history · DeliveryPierwszy komercyjny przeładunek w terminalu odbył się we wtorek, 15 lipca, a obsłużony został statek ECOMAL II.

    year taken from the source's publication date (22 Jul 2026)

    Stage historyPierwszy etap rozruchu technologicznego zakończył się sukcesem, do próbnych zawinięć doszło m.in. w maju 2026 r. Tamten etap testów rozpoczął się od rozładunku zbiornikowca Nordic Saga, który dostarczył etanol z Holandii.
  6. Energetyka2430 Jan 2024
    Stage history
    Stage historyInformując o postępie robót przy budowie terminala przeładunkowego na Martwej Wiśle, Orlen przypomniał, że inwestycja rozpoczęła się w styczniu 2023 r., jej zakończenie planowane jest na 2025 r., a wartość kontraktu to około 500 mln zł.