Świnoujście Offshore Terminal – ORLEN Neptun Offshore Wind Farm Installation Terminal

completedstage: operationaldelivered
EUR 39 million
programme budget (multi-year) · data from 2025net or gross: not recorded≈ PLN 168 million (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Poland's first installation terminal for offshore wind farms, put into operation at the port of Świnoujście in June 2025 (official opening on 10 June 2025). The facility, owned by ORLEN Neptun of the ORLEN Group, occupies approx. 20 ha and has two quays with a combined length of approx. 500 m, adapted for handling the largest jack-up and heavy-lift vessels as well as offshore wind farm components weighing up to 24,000 tons. The value of the investment was almost EUR 39 million. The terminal's target capacity is more than 80 offshore wind turbines per year. The terminal serves as both an installation and a marshalling port, and its first tenant was the Ocean Winds consortium (the BC-Wind project). An expansion is planned by 2030 to add quays nos. 3 and 4 (530 m in total, ultimately more than 1 km of quays) and a storage yard with an area of approx. 46 ha, initially estimated at approx. PLN 210 million, though funding for it is currently lacking (an application to the EU's CEF 2 instrument did not obtain support).

How it went

Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[3]
Utilisationin use[6]
active tenants leasing/using the terminal for offshore wind projects
Current
2 najemców w ciągu ok. 3 miesięcy od otwarcia: Ocean Winds (BC-Wind, wynajmuje niemal całą powierzchnię terminalu) i Smulders (elementy SIP dla Baltica 2: dostawa, składowanie, montaż) (2025)
Capacity or target
cały terminal (ok. 20 ha, dwa nabrzeża, ok. 500 m); projektowa przepustowość ponad 80 morskich turbin rocznie
Unit
tenants

Timeline

  1. DeliveryJun 2025

Change history

  • Jun 2025stage: operational

Significance

The terminal is the first in Poland and one of the most modern in Europe as an installation base for offshore wind farms, giving the national offshore energy sector its own logistics base on the Baltic and strengthening Świnoujście's role as the region's maritime energy hub. It serves not only the ORLEN Group's projects (Baltic East, Baltic West) but also external domestic and foreign operators, including Ocean Winds and Smulders, and approx. 95 Polish companies were involved in its construction. The planned doubling of the area by 2030 is to enable the parallel handling of the construction of two wind farms on the Baltic.

Sources 8 · 5 independent · 7 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. ORLEN Neptun
    Delivery
    Delivery · LocationW czerwcu 2025 r. w porcie w Świnoujściu uruchomiony został pierwszy w Polsce
  2. Polski Portal Morski (polskamorska.pl)8 Jun 2026
  3. WNP.plJun 2026
    StatusStageCostDelivery
    Status · DeliveryBudowa terminalu trwała ponad rok, prace zakończono w 2025 r.
    StageTeraz zajmuje on ok. 20 ha, dysponuje dwoma nabrzeżami o łącznej długości ok. 500 m
    CostWartość projektu to prawie 39 mln euro
  4. Świnoujście Offshore Terminal / ORLEN10 Jun 2025
    Investor
    InvestorThe agreement signed by ORLEN Neptun with Ocean Winds' Spanish-French consortium concerns the lease of almost the entire terminal area
  5. ORLEN10 Jun 2025
  6. ORLEN15 Sep 2025
    Utilisation
    UtilisationOpened only a few months ago, the Świnoujście Offshore Terminal has already established itself as the leading installation hub for offshore wind in the Baltic Sea.