← all projects
🚆Transportstrategic

S19 Rzeszów Południe – Babica (TBM tunnel)

under construction stage: construction delayed
3.0 bn PLN
programme budget (multi-year) · data from 20 Feb 2026 ≈ 3.0 bn PLN (value-by-stage, est., nominal) funding: state budget, EU – FEnIKS programme (almost PLN 1.5 billion)

Construction of a 10.3 km section of the S19 expressway between the Rzeszów Południe and Babica interchanges, carried out by GDDKiA along the Via Carpatia route. The key structure is a twin-bore tunnel 2,255 m long, bored by the TBM "Karpatka" – the first such structure in Podkarpackie Voivodeship. Construction work began in April 2022; after methane was detected in the rock mass, work was suspended and the contractual deadline was moved by an annex from autumn 2026 to 7 January 2028. The first tunnel bore was excavated in December 2025, and boring of the second bore has been underway since June 2026. The planned total cost exceeds PLN 3 billion, with EU funding (FEnIKS) of nearly PLN 1.5 billion.

How it went

Assessment: too early to assess. Signals only where documented.

Delivery partial
Schedule delayed

Timeline

Slip: +19 mo. vs. the original date

  1. Construction start Apr 2022
  2. Original date 2026
  3. Current date 7 Jan 2028

Change history

  • Apr 2022 stage: construction

Significance

The section closes the expressway exit from Rzeszów to the south along the international Via Carpatia corridor. The 2,255 m tunnel will be the first structure of its kind in Podkarpackie Voivodeship, and the project, with a planned cost of over PLN 3 billion, is among the most expensive road sections in the region; nearly PLN 1.5 billion comes from EU funds. The methane detected and the associated redesign of the TBM made the project a prominent example of geological risk in Polish road megaprojects, with a two-year deadline shift (from 2026 to 2028).

Sources 6 · 3 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. Podkarpacki Urząd Wojewódzki w Rzeszowie 20 Feb 2026
    CostInvestorDescription
    Cost „Planowany, całkowity koszt realizacji tego odcinka drogi ekspresowej S19 wynosi ponad 3 mld zł."
    Investor „GDDKiA podpisała pierwszą w tym roku umowę o dofinansowanie z Programu Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS)"
    locations „pierwszy taki obiekt w woj. podkarpackim"
  2. Ministerstwo Infrastruktury (gov.pl) 10 Dec 2025
    Current dateStageDescription
    Current date „zakończenie prac planowane jest w styczniu 2028 r."
  3. Generalna Dyrekcja Dróg Krajowych i Autostrad (gov.pl)
    Current dateInvestorStatus
  4. Rynek Infrastruktury 3 Jun 2025
    Original dateCurrent dateSignificance
    Original date „Początkowo założono, że tunel zostanie wykonany w ciągu 54 miesięcy od podpisania umowy z wyłączeniem okresów zimowych. W tym wariancie budowa zakończyłaby się jesienią 2026 roku."
    Current date „Zgodnie z zawartym aneksem, termin na ukończenie prac to 7 stycznia 2028 r."
  5. Podkarpacki Urząd Wojewódzki w Rzeszowie 13 Feb 2026
    Construction startStage historyDescription
    Construction start „w kwietniu 2022 r. rozpoczęły się roboty budowlane"
  6. Inżynieria.com 24 Jun 2026
    StatusStageDescription
    Status „TBM Karpatka rozpoczęła drążenie drugiej, prawej nawy tunelu"
    Stage „wydrążono około 10 m tunelu właściwego"