S19 Rzeszów Południe – Babica (TBM tunnel)
Construction of a 10.3 km section of the S19 expressway between the Rzeszów Południe and Babica interchanges, carried out by GDDKiA along the Via Carpatia route. The key structure is a twin-bore tunnel 2,255 m long, bored by the TBM "Karpatka" – the first such structure in Podkarpackie Voivodeship. Construction work began in April 2022; after methane was detected in the rock mass, work was suspended and the contractual deadline was moved by an annex from autumn 2026 to 7 January 2028. The first tunnel bore was excavated in December 2025, and boring of the second bore has been underway since June 2026. The planned total cost exceeds PLN 3 billion, with EU funding (FEnIKS) of nearly PLN 1.5 billion.
How it went
Assessment: too early to assess. Signals only where documented.
Timeline
Slip: +19 mo. vs. the original date
- Construction start Apr 2022
- Original date 2026
- Current date 7 Jan 2028
Change history
- Apr 2022 stage: construction
Significance
The section closes the expressway exit from Rzeszów to the south along the international Via Carpatia corridor. The 2,255 m tunnel will be the first structure of its kind in Podkarpackie Voivodeship, and the project, with a planned cost of over PLN 3 billion, is among the most expensive road sections in the region; nearly PLN 1.5 billion comes from EU funds. The methane detected and the associated redesign of the TBM made the project a prominent example of geological risk in Polish road megaprojects, with a two-year deadline shift (from 2026 to 2028).
Sources 6 · 3 archived
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- Podkarpacki Urząd Wojewódzki w Rzeszowie 20 Feb 2026CostInvestorDescription
Cost „Planowany, całkowity koszt realizacji tego odcinka drogi ekspresowej S19 wynosi ponad 3 mld zł."
Investor „GDDKiA podpisała pierwszą w tym roku umowę o dofinansowanie z Programu Fundusze Europejskie na Infrastrukturę, Klimat, Środowisko (FEnIKS)"
locations „pierwszy taki obiekt w woj. podkarpackim"
- Ministerstwo Infrastruktury (gov.pl) 10 Dec 2025Current dateStageDescription
Current date „zakończenie prac planowane jest w styczniu 2028 r."
- Generalna Dyrekcja Dróg Krajowych i Autostrad (gov.pl)Current dateInvestorStatus
- Rynek Infrastruktury 3 Jun 2025Original dateCurrent dateSignificance
Original date „Początkowo założono, że tunel zostanie wykonany w ciągu 54 miesięcy od podpisania umowy z wyłączeniem okresów zimowych. W tym wariancie budowa zakończyłaby się jesienią 2026 roku."
Current date „Zgodnie z zawartym aneksem, termin na ukończenie prac to 7 stycznia 2028 r."
- Podkarpacki Urząd Wojewódzki w Rzeszowie 13 Feb 2026Construction startStage historyDescription
Construction start „w kwietniu 2022 r. rozpoczęły się roboty budowlane"
- Inżynieria.com 24 Jun 2026StatusStageDescription
Status „TBM Karpatka rozpoczęła drążenie drugiej, prawej nawy tunelu"
Stage „wydrążono około 10 m tunelu właściwego"