Purchase of 20 Pesa Dart ED161 electric multiple units for PKP Intercity
On 23 May 2014, PKP Intercity S.A. and Pojazdy Szynowe Pesa Bydgoszcz S.A. signed a contract for the purchase of 20 Pesa Dart electric multiple units (series designation ED161). The value of the contract was PLN 1,320,626,400, of which PLN 1,008,600,000 was for the delivery of the trains and PLN 312,026,400 for a 15-year maintenance and repair package. PKP Intercity financed the project from its own funds and from EU co-financing from the Cohesion Fund under the Infrastructure and Environment Operational Programme, in the amount of PLN 574,050,400. The vehicles, built at Pesa's Bydgoszcz factory, are designed for a maximum speed of 160 km/h. The first train entered passenger service on 29 December 2015 on the Warsaw–Lublin route; the last of the 20 trains entered service on 20 February 2016, when PKP Intercity took delivery of the entire ordered fleet. The factory had only about a year and a half to build the 20 trains and did not manage to deliver all of them by the contractual deadline of 14 December 2015, which temporarily risked the loss of more than PLN 600 million in EU funds; the situation was resolved with an amendment to the contract.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section
- Current
- 20 pociągów odebranych i wprowadzonych do eksploatacji (ostatnie 20 lutego 2016)
- Capacity or target
- 20 zamówionych zespołów trakcyjnych
Timeline
Slip: +2 mo. vs. the original date
- Construction start23 May 2014
- Original date14 Dec 2015
- Delivery20 Feb 2016
Significance
The purchase of 20 Pesa Dart ED161 electric multiple units was one of the largest rolling-stock contracts of PKP Intercity in that period and, at the same time, as the manufacturer described it, the most difficult contract in the history of Bydgoszcz-based Pesa, owing to the tight delivery schedule. The new, air-conditioned trains with a maximum speed of 160 km/h were deployed, among other routes, on the lines from Warsaw to Lublin and Białystok, where significant increases in passenger numbers were recorded. The contract, co-financed from the EU Cohesion Fund, also covered 15 years of maintenance and repairs of the rolling stock by the manufacturer.
Sources 4 · 3 independent · 4 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Rynek Kolejowy23 May 2014CostConstruction startInvestorFunding
CostWartość kontraktu to 1 320 626 400 zł, z czego za dostawę wykonawca otrzyma 1 008 600 000, a za serwis 312 026 400 zł.
Construction start · InvestorPKP Intercity i Pojazdy Szynowe Pesa Bydgoszcz podpisały umowę na zakup 20 elektrycznych zespołów trakcyjnych.
FundingPKP Intercity sfinansuje projekt ze środków własnych oraz unijnych pochodzącychz funduszu spójności w ramach Programu Operacyjnego Infrastruktura i Środowisko w wysokości 574 050 400 zł.
- PKP Intercity S.A.
- Rynek KolejowyFeb 2016StatusStageDeliveryOriginal dateSchedule
Status · DeliveryPKP Intercity odebrało ostatni pociąg Pesa Dart. Wszystkie pojazdy są już zatem własnością PKP Intercity.
Stage · DeliveryOstatnie weszły do eksploatacji w sobotę 20 lutego.
year taken from the source's publication date (Feb 2016)
Original date · SchedulePóźną jesienią ubiegłego roku było już jasne, że z dostawą wszystkich pociągów do 14 grudnia Pesie nie uda się zdążyć.
- Prywatna Strona Miłośnika Komunikacji Miejskiej i SzynowejUtilisation
UtilisationDopiero na początku kwietniu 2016 roku ostatecznie wszystkie jednostki weszły do regularnej służby.