🚆Transportstrategic

Reconstruction of national road DK18 to A18 motorway standard (southern carriageway)

completed stage: operational delivered
900 mln PLN
programme budget (multi-year) · data from Oct 2023 ≈ 900 mln PLN (value-by-stage, est., nominal)

The reconstruction of the southern carriageway of the former national road No. 18 (a pre-war concrete route colloquially known as the "road of shame") to A18 motorway standard, on the section from the state border with Germany in Olszyna to the Golnice junction in Lower Silesia. As a result of the second stage of the investment, the entire dual-carriageway A18 motorway, 70 km long and running through the Lubuskie and Dolnośląskie voivodeships, obtained motorway parameters and status. The investor was the General Directorate for National Roads and Motorways (GDDKiA). The works included a new surface for the southern carriageway as well as the reconstruction and construction of bridge structures; the last, more than 20-kilometer section from the border of the Lubuskie and Dolnośląskie voivodeships to the Golnice junction was made available to drivers on 13 October 2023, completing the entire investment.

How it went

Assessment: settled. Signals only where documented.

Delivery delivered
Schedule on time
Utilisation in use
Scope as announced
average daily vehicle traffic (AADT)
750,010,000.3 / 0 vehicles/day (2015 (measurement from before the reconstruction; the route is an active E36 transit corridor to Berlin))

Timeline

  1. Announced Aug 2018
  2. Original date 2023
  3. Current date 2023
  4. Delivery 13 Oct 2023

Change history

  • 13 Oct 2023 stage: operational

Significance

The completion of the reconstruction of the southern carriageway finished the construction of the A18 motorway along its entire 70-kilometer length from the border with Germany in Olszyna to the Golnice junction, eliminating the notoriously degraded pre-war concrete surface criticized by drivers. The modern dual-carriageway route improves international transit traffic toward Berlin and the connection of western Poland (the Lubuskie and Dolnośląskie voivodeships) with the motorway network. The investment, worth nearly PLN 900 million, included a new surface as well as the reconstruction and construction of bridge structures.

Sources 5 · 3 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. Ministerstwo Infrastruktury 13 Oct 2023
    StatusStageStage historyDeliveryAnnounced
    name.pl „Zakończyły się prace związane z przebudową do standardu autostradowego jezdni południowej DK18"
    Announced „decyzja Ministra Infrastruktury z sierpnia 2018 r."
    Original date „13 października 2023 r. udostępniono do ruchu ostatni, ponad 20-kilometrowy odcinek"
  2. GDDKiA Oddział Zielona Góra 13 Oct 2023
    CostInvestor
    Stage „Udostępnienie drogi do ruchu w całym zakresie tj. w przekroju 2 + 2 na odcinku od granicy województw lubuskiego i dolnośląskiego do węzła Golnice, wieńczy II etap budowy autostrady A18."
    Cost „Koszt przebudowy całego odcinka od granicy w Olszynie do węzła Golnice to blisko 900 mln zł."
    Investor „Generalna Dyrekcja Dróg Krajowych i Autostrad- Oddział Zielona Góra"
    locations „To oznacza, że cała droga o długości 70 km zyskała parametry i status autostrady"
  3. TVN24 Biznes 13 Oct 2023
    StatusDelivery
    stage_events[0] „Już dziś kierowcy będą mogli przejechać całym odcinkiem autostrady A18 Olszyna-Golnice bez utrudnień."
  4. Ministerstwo Infrastruktury 27 Jan 2021
    OutcomeSchedule
    Schedule „Do 2023 roku ta trasa stanie się pełnoprawną autostradą A18."
  5. Wikipedia
    OutcomeUtilisation
    Utilisation „W 2015 drogą przejeżdżało 7,5–10 tys. pojazdów na dobę, w tym 3 tys. pojazdów ciężarowych z przyczepą."