← all projects
🏭Industrystrategic

Pyrometallurgy Modernisation Programme – flash furnace at the Głogów Copper Smelter

completedstage: operationaldelivereddelayedover budget
PLN 2.5 billion
programme budget (multi-year) · data from 2017net or gross: not recorded≈ PLN 2.5 billion (value-by-stage, est., nominal)funding: multilateral development bankLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Modernisation of the pyrometallurgical line at the Głogów I plant at the Głogów Copper Smelter, owned by KGHM Polska Miedź S.A. The key element of the programme was the replacement of the worn-out shaft-furnace technology with a flash furnace, described as the world's largest flash-and-electric furnace installation. The new production line reached an output of approx. 250,000 tonnes of blister copper per year and allows smelting to be conducted in a technologically cleaner and lower-emission form. Completion of the work was originally planned for 2015 at an assumed cost of under PLN 2 billion; ultimately the construction of the new line cost more than PLN 2.5 billion. The ceremonial opening of the installation took place in January 2017 with the participation of the President of the Republic of Poland. On 3 October 2017, shortly after start-up, a failure of the waste-heat boiler occurred (the collapse of a so-called sinter overhang), which halted the furnace's operation for nearly a month; from 19 October a technical start-up of the roasting installation was carried out, on 25 October the burners of the roasting furnace were lit, and the return of the Głogów I Copper Smelter to full production capacity was planned for the first half of November 2017.

How it went

Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. How to read this section

Deliverydelivered[2]
Scheduledelayed[5]
Budgetover budget[5]
Utilisationin use[7]
production capacity of the Głogów I Copper Smelter (electrolytic copper) / flash furnace (blister copper)
Current
pełna zdolność produkcyjna osiągnięta w XI 2017; instalacja w ruchu ciągłym (2017-2026)
Capacity or target
ok. 240 tys. ton miedzi elektrolitycznej/rok (Głogów I); piec zawiesinowy ~250 tys. ton miedzi blister/rok
Unit
t/yr

Timeline

Slip: about 2 years vs. the original date (given as a year)

  1. Original date2015
  2. Delivery2017

Change history

  • Jan 2017stage: operational

Significance

The programme secured the continuation of copper production at KGHM's largest smelting plant, replacing the obsolete shaft-furnace technology with a modern flash furnace with an output of approx. 250,000 tonnes of blister copper per year. The new installation reduces smelting costs and emissions of harmful gases, and according to KGHM is to allow production to be maintained for further decades. The failure of the waste-heat boiler in October 2017 caused a nearly month-long shutdown of the new installation, translating into a loss of electrolytic copper output and financial losses estimated in media reports at several hundred million złoty.

Sources 8 · 4 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Forsal.pl19 Jan 2017
    CostInvestor
    Cost · InvestorPonad 2,5 mld zł kosztowała budowa nowej linii produkcyjnej w należącej do KGHM Hucie Miedzi Głogów.
  2. StrefaInwestorow.pl23 Jan 2017
    StatusStageDelivery
    Status · LocationKGHM uruchomił instalację pieca zawiesinowego i elektrycznego w hucie w Głogowie
    Stage · DeliveryW Hucie Miedzi Głogów w piątek 20 stycznia 2017 roku, w towarzystwie Prezydenta RP Andrzeja Dudy, uroczyście została uruchomiona
    DeliveryW Hucie Miedzi Głogów w piątek 20 stycznia 2017 roku, w towarzystwie Prezydenta RP Andrzeja Dudy, uroczyście została uruchomiona największa na świecie instalacja pieca zawiesinowego i pieca elektrycznego, tworząc tym samym najnowocześniejszą linię produkcji hutniczej miedzi.
  3. Utrzymanie Ruchu8 Nov 2013
    Original date
    Original dateZmiana technologii, która wiąże się z budową pieca zawiesinowego, w zakładzie „Głogów I” zakończy się w 2015 roku.
  4. KGHM Polska Miedź S.A.2 Nov 2017
  5. Forsal.pl2017
    ScheduleBudget
    Schedule · BudgetZ dokumentów, do których dotarł DGP, wynika, że głogowska instalacja, choć droższa niż zakładano i oddana do użytku z okołorocznym poślizgiem, została dobrze oceniona przez branżowe autorytety
  6. KGHM Polska Miedź S.A.
  7. KGHM Polska Miedź S.A.
    Utilisation
    UtilisationCurrently the Głogów Copper Smelter and Refinery has a production capacity of approx. 475 thousand tonnes of electrolytic copper per year, of which Głogów I has a capacity of 240 kt/year and Głogów II has a capacity of 235 kt/year.
  8. Funding
    FundingStrategicznym partnerem finansowym KGHM Polska Miedź S.A. przy inwestycji modernizacji pirometalurgii jest Europejski Bank Inwestycyjny, który kredytowo wsparł jej realizację