🚆Transportstrategic

Improving access to the Port of Gdańsk – modernization of waterway 2 (4 quays)

under constructionstage: construction
PLN 533 million
programme budget (multi-year) · data from 2022net or gross: not recorded≈ PLN 533 million (value-by-stage, est., nominal)planned funding: EU fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A programme to modernize four quays of the Inner Port in Gdańsk (Wiślane, Bytomskie, Rudowe III and Węglowe) with a total length of 1916 m, together with underground and rail infrastructure and the deepening of the seabed. The investor is Zarząd Morskiego Portu Gdańsk SA, and the undertaking, worth approximately PLN 533 million, is mostly (approximately PLN 453 million, 85%) financed from the EU CEF instrument. Construction work began in 2024 with the Rudowe and Bytomskie quays (contractor PORR), while the expansion of the Wiślane quay (DORACO) and the Węglowe quay (Budimex) was planned for subsequent years; the Bytomskie quay was completed in December 2025.

How it went

Assessment: too early to assess, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

No source calls this a delay and the card makes no assessment here, but the dates recorded on this project differ by 2 years: originally 2026, currently 2028.

Deliverypartial[6]

Timeline

  1. Announced2022
  2. Construction startMar 2024
  3. Original date2026
  4. Current date2028

Change history

  • Mar 2024stage: construction
  • Mar 2022stage: announced

Significance

The expansion of four quays of the Inner Port increases the handling capacity and accessibility of the Port of Gdańsk for larger vessels, including through the deepening of the seabed at the Wiślane quay to 12 m technical depth and the adaptation of the Rudowe III quay to vessels of up to 35,000 DWT. The investment modernizes 1916 m of handling frontage together with rail and underground infrastructure, strengthening the role of Gdańsk in the trans-European TEN-T transport network. The programme is largely financed from EU funds (approximately PLN 453 million, 85% of costs under the CEF instrument).

Sources 7 · 6 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Infrastruktury (gov.pl)15 Mar 2022
    CostInvestorAnnouncedOriginal date
    CostCałkowita wartość inwestycji to ok. 533 mln zł
    InvestorTa wieloletnia inwestycja Zarządu Morskiego Portu Gdańsk SA
    Announced · Original datePlanowany okres realizacji inwestycji to lata 2022-2026
    LocationPort Gdańsk, w ramach projektu „Poprawa dostępu do Portu Gdańsk – modernizacja toru wodnego 2”, przygotowuje się do modernizacji czterech kolejnych nabrzeży.
  2. Netka.gda.pl14 Mar 2022
  3. PortalMorski.pl21 Mar 2024
    Construction startStage history
    Construction startPrezes Portu Gdańsk Krzysztof Kaczmarek podpisał dwie umowy z PORR SA na modernizację nabrzeży
    Stage historyŁączna wartość podpisanych dzisiaj umów na realizację robót budowlanych wynosi 142 mln zł brutto
  4. Zarząd Morskiego Portu Gdańsk SA (portgdansk.pl)9 Jul 2025
    Current date
    Current datethe work is scheduled for completion in the second quarter of 2028
  5. Gdansk.pl11 Mar 2025
  6. Obserwator Logistyczny18 Dec 2025
    StatusStageDelivery
    Status · StageAktualnie trwają prace przy Nabrzeżu Rudowym, Wiślanym oraz Węglowym
    DeliveryW Porcie Gdańsk zakończono kolejną kluczową inwestycję, która znacząco wpłynie na rozwój tego największego polskiego portu morskiego. Rozbudowano Nabrzeże Bytomskie, będące pierwszym z czterech elementów szerokiego programu modernizacji nabrzeży.
  7. Funding
    FundingCałkowita wartość projektu to ok. 533 mln zł, z czego dofinansowanie ze środków unijnych, w wysokości 85 proc. kosztów, stanowić będzie nieco ponad 453 mln zł.