Improving access to the Port of Gdańsk — modernization of waterway 2 (4 quays)
A programme to modernize four quays of the Inner Port in Gdańsk (Wiślane, Bytomskie, Rudowe III and Węglowe) with a total length of 1916 m, together with underground and rail infrastructure and the deepening of the seabed. The investor is Zarząd Morskiego Portu Gdańsk SA, and the undertaking, worth approximately PLN 533 million, is mostly (approximately PLN 453 million, 85%) financed from the EU CEF instrument. Construction work began in 2024 with the Rudowe and Bytomskie quays (contractor PORR), while the expansion of the Wiślane quay (DORACO) and the Węglowe quay (Budimex) was planned for subsequent years; the Bytomskie quay was completed in December 2025.
How it went
Assessment: too early to assess. Signals only where documented.
Timeline
Slip: +24 mo. vs. the original date
- Announced Mar 2022
- Construction start Mar 2024
- Original date 2026
- Current date 2028
Change history
- Mar 2024 stage: construction
- Mar 2022 stage: announced
Significance
The expansion of four quays of the Inner Port increases the handling capacity and accessibility of the Port of Gdańsk for larger vessels, including through the deepening of the seabed at the Wiślane quay to 12 m technical depth and the adaptation of the Rudowe III quay to vessels of up to 35,000 DWT. The investment modernizes 1916 m of handling frontage together with rail and underground infrastructure, strengthening the role of Gdańsk in the trans-European TEN-T transport network. The programme is largely financed from EU funds (approximately PLN 453 million, 85% of costs under the CEF instrument).
Sources 6 · 5 archived
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- Ministerstwo Infrastruktury (gov.pl) 15 Mar 2022CostInvestorAnnouncedOriginal dateStage history
Cost „Całkowita wartość inwestycji to ok. 533 mln zł"
Investor „Ta wieloletnia inwestycja Zarządu Morskiego Portu Gdańsk SA"
Announced „Planowany okres realizacji inwestycji to lata 2022-2026"
locations[0] „Rozbudowane mają zostać nabrzeża portu wewnętrznego o łącznej długości 1916 metrów"
- Netka.gda.pl 14 Mar 2022CostInvestor
- PortalMorski.pl 21 Mar 2024Construction startStage history
Construction start „Prezes Portu Gdańsk Krzysztof Kaczmarek podpisał dwie umowy z PORR SA na modernizację nabrzeży"
stage_events[1].stage „Łączna wartość podpisanych umów na realizację robót budowlanych wynosi 142 mln zł brutto"
- Zarząd Morskiego Portu Gdańsk SA (portgdansk.pl) 9 Jul 2025Current date
Current date „the work is scheduled for completion in the second quarter of 2028"
- Pół kilometra nowego nabrzeża. Duża inwestycja w Porcie Gdańsk. Nabrzeże Węglowe / Budimex ↗ archived ✓Gdansk.pl 11 Mar 2025Stage
- Obserwator Logistyczny 18 Dec 2025StatusStage
Status „Aktualnie trwają prace przy Nabrzeżu Rudowym, Wiślanym oraz Węglowym"