Pomeranian Metropolitan Railway (new line Gdańsk Wrzeszcz – Airport – Kartuzy/Kościerzyna)
The Pomeranian Metropolitan Railway is a newly built suburban railway line connecting Gdańsk Wrzeszcz with Lech Wałęsa Airport and with railway line no. 201 towards Kartuzy and Kościerzyna, partly following the route of the former Kashubian Railway, closed since 1945. The investor was Pomorska Kolej Metropolitalna S.A., a company established by the Pomeranian voivodeship self-government. It was the first line in the country built not by PKP but by a voivodeship self-government. The general contractor was the Polish-Spanish consortium of Budimex S.A. (leader) and Ferrovial Agroman S.A. Construction officially began and the founding deed was signed on 1 July 2013, the ceremonial inauguration took place on 30 August 2015, and the line was put into service in September 2015. The length of the line, including the connector towards Kościerzyna, is approximately 19.5 km, with eight stops built along the route. The construction cost was originally estimated at PLN 769.9 million net; the total project value, after including PLN 186.5 million in land value transferred for the investment, came to PLN 907 million net, including PLN 500.9 million in funding from the Infrastructure and Environment Operational Programme.
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
- Current
- linia czynna i eksploatowana od września 2015 r.
Timeline
- Construction start1 Jul 2013
- DeliverySep 2015
Significance
The Pomeranian Metropolitan Railway was the first railway line in Poland built by a voivodeship self-government rather than by PKP, making it a model example of a self-government rail investment. The new line connected Gdańsk with Lech Wałęsa Airport by rail for the first time and revived rail transport in the corridor of the former Kashubian Railway towards Kartuzy and Kościerzyna, closed since 1945. The project was the flagship transport investment of the Pomeranian voivodeship self-government and an important element of the transport system of the Tricity (Gdańsk-Gdynia-Sopot) agglomeration.
Sources 6 · 4 independent · 4 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
- Wikipedia (pl)StatusCostConstruction startInvestorFundingDelivery
Status · Deliveryoddanie linii do użytku miało miejsce dwa dni później, 1 września
CostCałkowita wartość projektu PKM – po uwzględnieniu 186,5 mln zł wartości gruntów przekazanych pod inwestycję – wynosiła 907 mln zł netto
Construction startOficjalne rozpoczęcie budowy i podpisanie aktu erekcyjnego nastąpiło 1 lipca 2013.
InvestorSpółka Pomorska Kolej Metropolitalna została powołana celem budowy i utrzymania linii kolejowych
FundingSzacowany pierwotnie koszt budowy linii wynosił 769,9 mln zł netto (w tym 500,9 mln zł z Programu Operacyjnego Infrastruktura i Środowisko).
- Pomorska Kolej Metropolitalna S.A.Delivery
DeliveryDzięki uruchomionej we wrześniu 2015 r. linii PKM tysiące mieszkańców Pomorza może obecnie szybciej i wygodniej dojechać do pracy, szkoły lub na zakupy, a potem równie sprawnie wrócić do domu.
- Inżynier BudownictwaStage
StageOd 1 września 2015 r. dwutorowa Pomorska Kolej Metropolitalna stanowi najszybszy
- Rynek Kolejowy1 Sep 2025StatusStageUtilisation
Status · StageW ramach projektu Pomorskiej Kolei Metropolitalnej w dniu 1 września po raz pierwszy na nowo powstałe linie kolejowe nr 248 i 253, wybudowane częściowo w śladzie historycznej Kolei Kokoszkowskiej, wyruszyły regularne pociągi pasażerskie.
UtilisationObecnie z połączeń PKM korzysta aż 450 tys. osób w ciągu miesiąca.
- WNP.PL (Portal Gospodarczy)7 May 2013
- Pomorska Kolej Metropolitalna S.A. (pkm-sa.pl)27 Sep 2010Investor
InvestorPomorska Kolej Metropolitalna S.A. została powołana 11 czerwca 2010 r. jako jednoosobowa spółka Samorządu Województwa Pomorskiego.