New Łódź Fabryczna Station (with multimodal hub)

completedstage: operationaldelivereddelayed
1.8 bn PLN
contract value · data from 2016incl. VAT≈ 1.8 bn PLN (value-by-stage, est., nominal)

The reconstruction of Łódź Fabryczna station into an underground, multi-level railway station integrated with a multimodal hub combining suburban and long-distance rail, bus, urban transport, and car traffic. Four platforms were placed underground, and the facility was designed as a through station for the future cross-city tunnel and the planned high-speed rail network. The station was cleared for operation in December 2016.

How it went

Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[1]
Scheduledelayed[1]
Utilisationin use[6]
annual passenger throughput of ŁKA (facility in active operation as a terminus station); the target daily technical capacity refers to full expansion as a through station after the opening of the cross-city tunnel, and is not a current ridership target
Current
2 206 590 pasażerów ŁKA w 2024 r. (ok. 2,21 mln); najpopularniejsza stacja kolejowa w regionie łódzkim (dodatkowo obsługa PKP Intercity)
Capacity or target
do 200 tys. pasażerów dziennie – projektowa przepustowość techniczna dla stacji przelotowej po ukończeniu tunelu średnicowego (ceiling projektowy, nie prognoza frekwencji)
Unit
passengers

Timeline

Slip: +22 mo. vs. the original date

  1. Original dateFeb 2015
  2. Delivery11 Dec 2016

Change history

  • 11 Dec 2016stage: operational

Significance

The largest underground multimodal station of its kind in Poland, integrating rail, long-distance bus, urban transport, and car traffic in a single facility in the centre of Łódź. The facility remains a terminus until the completion of the cross-city tunnel connecting Łódź Fabryczna with the Łódź Kaliska and Łódź Żabieniec stations, whose opening has been repeatedly delayed; only after it is put into service will the station begin to function as a through station and fully use the infrastructure it was designed for.

Sources 12 · 6 independent · 8 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Gazeta Prawna11 Dec 2016
    StatusDeliveryCostSchedule
    Status · Delivery · SchedulePo pięciu latach budowy o godz. 5:30 na peron Dworca Łódź Fabryczna wjechał pierwszy pociąg
    CostInwestycja kosztowała 1,75 mld zł brutto
  2. Wikipedia
    StageStage historyInvestor
    Stage · Stage historyIt was closed on 16 October 2011 as a part of a major redevelopment project to build a new railway station and transport interchange[1] and reopened on 11 December 2016.[2]
    InvestorOwner Polskie Koleje Państwowe S.A.
    LocationThe modernization of the Łódź – Warsaw line includes building a new station below ground level, just north of the site of the former Łódź Fabryczna station.
  3. TVN2411 Dec 2016
  4. Rynek Kolejowy
  5. Rynek Kolejowy
    Original date
    Original datePrace miały zakończyć się 28 lutego 2015 r.
  6. Urząd Miasta Łodzi
    Utilisation
    UtilisationStacja kolejowa z czterema peronami znajduje się na poziomie ulokowanym 16,5 m pod ziemią i jest w stanie odprawić nawet 200 tys. pasażerów dziennie.
  7. Rynek Kolejowy
    Utilisation
    Utilisation2 206 590 klientów łódzkiego przewoźnika
  8. ŁÓDŹ.PL
  9. Rynek Kolejowy30 May 2025
    Assessment
    Assessmentprzedłużenie prac o rok, czyli do 30 czerwca 2027 roku
  10. Funding
    FundingWysokość dofinansowania UE: 1,02 mld zł
  11. Funding
    FundingObecnie inwestycja ma zapewnione stabilne finansowanie krajowe.
  12. Funding
    FundingKomisja Europejska zatwierdziła 85,8 mln euro dofinansowania na budowę węzła multimodalnego