Modernization of line No. 201 Maksymilianowo – Gdynia (coal trunk line, access to the Port of Gdynia)
A comprehensive modernization, expansion and electrification of railway line No. 201 on the Maksymilianowo – Kościerzyna – Gdynia section (the historic coal trunk line). The programme includes the construction of a second track along most of the route, electrification, the reconstruction of Maksymilianowo station and the construction of a third track on the Gdańsk Osowa – Gdynia Główna section in order to increase the capacity of the freight corridor to the Port of Gdynia. The works are being carried out in stages. Contracts for successive sections are being signed and announced, including the Wierzchucin – Lipowa Tucholska section (contract of approx. PLN 915 million) and section C Gdańsk Osowa – Gdynia Główna (estimated value of over PLN 1.3 billion). Investor: PKP Polskie Linie Kolejowe.
How it went
Assessment: too early to assess, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section
Timeline
Slip: about 4 years vs. the original date (given as a year)
- Original date2028
- Current date2032
Change history
- 2 Oct 2025stage: tender
Significance
The modernization and electrification of the coal trunk line is intended to increase the capacity and speed of freight traffic towards the Port of Gdynia and to shorten passenger train journey times. Once the works are completed, the line will be double-track and electrified along the entire Maksymilianowo – Gdynia route, and triple-track on the Gdańsk Osowa – Gdynia Główna section, which will improve connections between the Tricity and the region as well as the handling of cargo at the port.
Sources 4 · 3 independent · 3 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- [1]Z Gdańska do Gdyni po trzech torach - ogłaszamy kolejny przetarg na modernizację trasy Bydgoszcz - Trójmiasto ↗archived ✓PKP Polskie Linie Kolejowe S.A.2 Oct 2025Stage historyInvestorFunding
Stage historyogłaszamy kolejny przetarg na modernizację trasy Bydgoszcz - Trójmiasto
InvestorProjekt będzie realizowany ze środków własnych PLK SA, budżetu państwa oraz Europejskiego Banku Inwestycyjnego
Locationodc. Gdańsk Osowa – Gdynia Główna
FundingProjekt będzie realizowany ze środków własnych PLK SA, budżetu państwa oraz Europejskiego Banku Inwestycyjnego.
- inzynieria.comStage
StageKolejne 27 km linii 201 do przebudowy. Kontrakt za 915 mln zł podpisany
- Rynek Kolejowy16 Apr 2025StatusCurrent dateOriginal dateSchedule
Status · Current dateaktualny harmonogram inwestycji zakłada zakończenie wszystkich planowanych prac na linii 201 pomiędzy Maksymilianowem a Gdynią dopiero w 2032 roku
Original datePKP Polskie Linie Kolejowe deklarowały wówczas, że prace na LK 201 zostaną zakończone w 2028 roku.
Locationprace na linii 201 pomiędzy Maksymilianowem a Gdynią
ScheduleNiestety jest już pewne, że nie uda się dotrzymać tego terminu.
- Funding
FundingInwestycji o wartości netto 5,4 mld zł przyznano unijne dofinansowanie na kwotę 4,6 mld zł w ramach programu Fundusze Europejskie na Infrastrukturę, Klimat i Środowisko 2021-2027.