🚆Transportstrategic

Modernization and expansion of Chopin Airport in Warsaw

in preparationstage: tender
940 mln PLN
programme budget (multi-year) · data from Jul 2025net or gross: not recorded≈ 940 mln PLN (value-by-stage, est., nominal)funding: PPL, bank loan (Pekao, PKO BP, BGK)

Polskie Porty Lotnicze, a State Treasury company, is running a programme to modernize and expand Chopin Airport in Warsaw (Okęcie) – the largest airport in Poland – to increase its capacity for the transitional period before the Central Communication Port opens. Under the investment, the number of parking stands for narrow-body aircraft is to grow from 62 to 83, for wide-body aircraft from 15 to 24, and the passenger terminal floor area from 165,000 to 189,115 m2; the target capacity is approx. 30 million passengers per year. The original cost estimate (PLN 1.6 billion) was lowered – according to PPL the works are to cost PLN 940 million plus a 40 percent reserve for unforeseen expenditures. In December 2025 PPL announced a tender for the reconstruction of the terminal and the southern pier (deadline for submitting applications by 2 February 2026), and in February 2026 a loan agreement for PLN 3.3 billion was signed with a consortium of banks Pekao, PKO BP and BGK, covering both the modernization of Chopin and the construction of Port Polska. Signing of the contract with the contractor is planned for April 2027, and delivery of the modernized infrastructure for 2029.

How it went

We have assessed this project, but none of the four axes is shown here: 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. Original date2029
  2. Current date2029

Change history

  • 29 Dec 2025stage: tender

Significance

The modernization is to secure the capacity of Poland's largest airport in the period until the opening of the Central Communication Port, so that – as PPL argues – it does not lose millions of passengers who would otherwise seek other airports. The expansion increases the terminal by approx. 15 percent of floor area (to 189,115 m2), the number of stands for wide-body aircraft by more than 60 percent (from 15 to 24), and for narrow-body aircraft by more than 30 percent (from 62 to 83), raising the airport's target capacity to approx. 30 million passengers per year. The investment is strategically tied to the schedule of the Central Communication Port and the construction of Port Polska – financed jointly from the PLN 3.3 billion loan – and its relatively low cost (PLN 940 million plus reserve) is presented as an economical, bridging solution maintaining air traffic in Warsaw for the coming years.

Sources 6 · 5 independent · 6 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Rzeczpospolita (turystyka.rp.pl)29 Dec 2025
    StageStage history
    Stage · Stage historyogłosiły długo zapowiadany przetarg na przebudowę terminala i pirsu południowego Lotniska Chopina
    Locationprzetarg na przebudowę terminala i pirsu południowego Lotniska Chopina
  2. Rzeczpospolita (rp.pl)1 Jul 2025
    Cost
    CostMa kosztować nie 1,6 mld zł, a 940 mln zł. plus 40 proc. rezerwy na nieprzewidziane wydatki.
  3. Rynek Lotniczy20 Feb 2026
    StatusInvestorFunding
    Statusz fazy planowania i opowieści przeszliśmy do fazy realizacji najważniejszej inwestycji w historii polskiego lotnictwa
    Investorumowę o wartości 3,3 mld zł na modernizację Lotniska Chopina i budowę Portu Polska
    FundingZ tych 3,3 mld zł ok. 2/3 zostanie wykorzystane do sfinansowania programu modernizacji Lotniska Chopina.
    FundingKredyt ma zostać spłacony przez PPL do roku 2032
  4. Bankier.pl20 Feb 2026
  5. TransInfo5 May 2025
    Original dateCurrent date
    Original date · Current dateotwarcie zmodernizowanej infrastruktury planowane jest na 2029
  6. WNP.pl