Maria Skłodowska-Curie Bridge (North Bridge) in Warsaw with the North Bridge Route
The Maria Skłodowska-Curie Bridge (originally called the North Bridge) is a road, tram, pedestrian and cycle bridge over the Vistula in the northern part of Warsaw, with a total length of 795 m, linking the districts of Bielany and Białołęka. It was built together with the North Bridge Route (now the Maria Skłodowska-Curie Bridge Route), a new arterial road running from the junction with Modlińska Street on the eastern bank to the Młociny interchange on the western bank. Construction began at the end of May 2009, and the road section of the bridge opened on 25 March 2012; the first tram line began operating on 21 January 2013. The investor was the City of Warsaw, with delivery carried out by the Stołeczny Zarząd Rozbudowy Miasta (SZRM). The scope of the investment included, among other things, the construction of a 4.3 km section of the route from the junction with Modlińska Street to the Młociny interchange; the stage I works (2009-2013) were valued at PLN 976,618,384, and the stage II works (2010-2012, contractor Skanska) at PLN 51.5 million. The total cost of the project was PLN 1,150,581,207, of which EU co-financing (the Cohesion Fund / Operational Programme Infrastructure and Environment) accounted for PLN 374,599,231, under an agreement between the City of Warsaw and the Centrum Unijnych Projektów Transportowych (Centre for EU Transport Projects).
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
Timeline
Significance
The Maria Skłodowska-Curie Bridge together with the North Bridge Route created a new road and tram link across the Vistula in the northern part of Warsaw, connecting the left-bank district of Bielany (the Młociny interchange) with the right-bank district of Białołęka (the junction with Modlińska Street). The investment, worth over PLN 1.15 billion and co-financed by the European Union, improved transport links for the rapidly growing districts of northern Warsaw and closed another section of the city's ring-road network.
Sources 7 · 4 independent · 5 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
- Stołeczny Zarząd Rozbudowy Miasta
- Wikipedia (pl)StatusStageCostConstruction startDeliveryInvestorFunding
Status · Stage · DeliveryOdcinek został oddany do użytku 25 marca 2012
CostCałkowity koszt projektu to 1 150 581 207 zł
Construction startbudowa rozpoczęta pod koniec maja 2009 roku
Investorumowę pomiędzy miastem stołecznym Warszawa a Centrum Unijnych Projektów Transportowych
Funding4 sierpnia 2010 roku podpisano umowę pomiędzy miastem stołecznym Warszawa a Centrum Unijnych Projektów Transportowych, która dotyczyła dofinansowania projektu „Budowa Trasy Mostu Północnego”.
- Wikipedia (pl)Delivery
DeliveryCzęść mostu dla ruchu drogowego została otwarta dla ruchu 25 marca 2012[11], zaś część mostu dla tramwajów, pieszych i rowerzystów miała zostać całkowicie ukończona pod koniec czerwca 2012.
- Funding
FundingProjekt jest dofinansowany z Europejskiego Funduszu Rozwoju Regionalnego, w ramach Programu Operacyjnego Infrastruktura i Środowisko
Fundingwynosi 374 599 231,59 PLN, a całkowita wartość dwóch etapów projektu to 1 150 581 207,21 zł. Projekt jest dofinansowany z Europejskiego Funduszu Rozwoju Regionalnego, w ramach Programu Operacyjnego Infrastruktura i Środowisko
- Money.pl (depesza PAP)24 Mar 2012
- Rynek Infrastruktury25 Mar 2012Status
StatusCieszę się, że most może służyć mieszkańcom Warszawy – mówiła obecna na uroczystości otwarcia mostu Patrycja Wolińska-Bartkiewicz, wiceminister transportu.
- Inżynier Budownictwa26 Mar 2012Cost
CostCałkowite koszty inwestycji wskazane w umowie to 1150,59 mln zł, koszty kwalifikowane – 944,52 mln zł.