W-Z Route in Łódź (Retkinia–Widzew tram line, extended to Olechów)
The W-Z Route is one of Łódź's most important transport arteries, linking two large residential districts: Retkinia in the west and Olechów (Widzew) in the east. A two-year rebuilding, extension and modernisation of the tram corridor, together with the accompanying road layout, was carried out in 2013–2015. Reconstruction began on 1 October 2013, and traffic on the route was restored in October 2015. The scope of works covered 13.2 km of route, the construction of more than 17 km of new tram track, seven integrated public-transport stops and four transfer points; the tram connection was extended to reach, among others, the Olechów district, where the line was extended by around 4 km. According to Grzegorz Nita, director of the Łódź Roads and Transport Authority, the base value of the investment was PLN 747 million, of which co-financing from the European Union (the Operational Programme Infrastructure and Environment) reached PLN 532 million; additional works during the rebuild cost around PLN 25 million and were financed by the city. The investor was the Łódź Roads and Transport Authority, a municipal unit of the Łódź City Office.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section
Timeline
Significance
The rebuilding of the W-Z Route was one of the flagship transport investments in Łódź under the 2007–2013 financial perspective, carried out largely with EU funds (the Operational Programme Infrastructure and Environment). The modernised east-west corridor, together with more than 17 km of new track, connected Łódź's two largest residential districts, Retkinia and Olechów, and brought the tram to the Olechów district, creating seven integrated stops and four transfer points that improved public transport in the city.
Sources 6 · 4 independent · 4 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
- PortalSamorzadowy.pl30 Oct 2015CostInvestorFunding
Cost"Wartość podstawowa inwestycji to 747 mln zł, z czego dofinansowanie z UE wyniosło 532 mln zł. Prace dodatkowe przy przebudowie trasy kosztowały ok. 25 mln zł i zostały sfinansowane przez miasto" - poinformował dyrektor Zarządu Dróg i Transportu Grzegorz Nita.
Investorpoinformował dyrektor Zarządu Dróg i Transportu Grzegorz Nita.
FundingWartość podstawowa inwestycji to 747 mln zł, z czego dofinansowanie z UE wyniosło 532 mln zł.
FundingPrace dodatkowe przy przebudowie trasy kosztowały ok. 25 mln zł i zostały sfinansowane przez miasto
- Wikipedia (pl)Construction startDelivery
Construction start1 października 2013 r. rozpoczęła się dwuletnia przebudowa trasy W-Z
DeliveryTrasę otwarto w październiku 2015 r[1].
- Rynek Kolejowy11 Jun 2014
- PortalSamorzadowy.pl2015
- Urbnews.pl31 Oct 2015Status
StatusPrzebudowa trasy W-Z w Łodzi trwała około 2 lat i kosztowała niemalże 800 mln zł.
- Super Express (Łódź)1 Nov 2015StatusStage
Status · StageW sobotni poranek (31 października), jako pierwszy po Trasie W-Z, przejechał tramwaj linii 10 z Retkini na Olechów.