Krakow Fast Tram stage III: Krowodrza Górka - Górka Narodowa

completed stage: operational
595 mln PLN
programme budget (multi-year) · data from 2017 ≈ 595 mln PLN (value-by-stage, est., nominal) funding: Cohesion Fund (POIiŚ 2014-2020), City of Kraków budget, government Programme supporting preparations for the 3rd European Games

Construction of stage III of the Krakow Fast Tram — a line approximately 5.5 km long of double track (approximately 11 km of track) connecting the Krowodrza Górka loop with the Górka Narodowa housing estate in the northern part of Krakow. The route was designed and built by a consortium of Intercor and Tor-Krak under a contract signed on 22 May 2017. The investment included, among other things, a two-level integrated interchange hub with a P+R car park and a bus terminal at Górka Narodowa, a road tunnel along Opolska Street, and further Park & Ride car parks. The total value of the project amounted to approximately PLN 595 million, of which approximately PLN 184 million was funding from the EU Cohesion Fund (OPI&E 2014–2020), and PLN 38 million came from the government programme supporting preparations for the 3rd European Games. Trams began running on the new route in September 2023.

Timeline

Slip: +44 mo. vs. the original date

  1. Construction start May 2017
  2. Original date 2020
  3. Delivery Sep 2023

Change history

  • Sep 2023 stage: operational
  • May 2017 stage: construction

Significance

The new line completed the northern section of the fast tram in Krakow and shortened travel time from the densely populated estates north of Opolska Street (Górka Narodowa, Prądnik Biały) to the city centre, connecting them to the KST network with Park & Ride car parks encouraging travellers to switch from cars. Uptake proved high from the outset — in the first month more than half a million passengers used the new connection. However, delivery was significantly delayed: the 2017 contract assumed construction within approximately 3.5 years, yet the trams did not begin running until September 2023.

Sources 4

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. Zarząd Inwestycji Miejskich w Krakowie
    Costcost.fundingInvestorConstruction startStage
    name.pl „budowie linii tramwajowej o długości ponad 5 km"
    Investor „Przedsiębiorstwo Usług Technicznych «INTERCOR» Sp. z o. o. oraz Przedsiębiorstwo Inżynieryjnych Robót Kolejowych «TOR-KRAK» Sp. z o. o."
    Construction start „Zgodnie z podpisaną 22 maja 2017 roku umową"
    Cost „Całkowita wartość projektu: 595 186 914,69 PLN"
  2. Ministerstwo Infrastruktury (gov.pl)
    StatusStageDeliverycost.funding
    Status „Od 4 września 2023 r. w Krakowie tramwaje zaczną kursować między Krowodrzą Górką a Górką Narodową."
    cost.funding „Pozyskano ok. 184 mln zł ze środków Funduszu Spójności w ramach Programu Operacyjnego Infrastruktura i Środowisko na lata 2014-2020."
    locations „tramwaje zaczną kursować między Krowodrzą Górką a Górką Narodową"
  3. Magiczny Kraków (krakow.pl) 25 Oct 2023
    StatusSignificance
  4. Rynek Kolejowy 10 Mar 2017
    Original date
    Original date „Trasa ma powstać w ciągu 3,5 roku od zawarcia umowy."