Izera / ElectroMobility Poland (Polish electric car)

cancelledstage: announceddelayedrestructuredabandonedwritten off
PLN 580 million
estimate · data from 2025net of VAT≈ PLN 580 million (value-by-stage, est., nominal)funding: state special fundLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Izera is the brand of the first Polish electric car, developed by the company ElectroMobility Poland S.A. (controlled by the State Treasury), established on 19 October 2016. The brand was officially presented on 28 July 2020, and the factory was planned in Jaworzno in the Śląskie Voivodeship, with series production originally announced for the third quarter of 2023. The deadlines were successively postponed (to 2024, and then to the fourth quarter of 2025), and the project – based partly on the platform of China's Geely – failed to secure financing. On 17 December 2024, the Minister of State Assets Jakub Jaworowski announced the end of the Izera project. After years of work and more than PLN 580 million in spending, neither the factory nor a finished vehicle was produced. The company redirected its activities towards building a production and development hub in Jaworzno with a new brand and the Taiwanese partner Foxconn (a separate successor project).

Why it failed

The Izera project, run by the company ElectroMobility Poland S.A. (majority State Treasury-owned) since 2016, aimed to launch production of the first Polish electric car at a factory in Jaworzno. Series production was originally planned for the third quarter of 2023, and was then postponed to 2024 and the fourth quarter of 2025. The project, which was based in part on the platform of the Chinese group Geely, failed to secure full financing by the end of 2023 and was suspended; a change of government and audits followed. On 17 December 2024, the Minister of State Assets Jakub Jaworowski announced the end of the Izera project, which was confirmed in April 2025 by the company's new CEO Tomasz Kędzierski. By the time the project was closed, with spending exceeding PLN 580 million, no factory or finished Izera-brand vehicle had been produced. The company's activity was redirected towards building a production hub in Jaworzno with a new brand and the Taiwanese partner Foxconn – this is a separate, successor undertaking.

How it went

Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverynot delivered[2]
Scheduledelayed[6]
Scopesuperseded[5]
Lossesknown sunk cost · PLN 580 million[2]
finished vehicle / factory
Current
0 units (brak fabryki i pojazdu) (until project closure 2024-12)
Capacity or target
fabryka w Jaworznie + seryjna produkcja auta

Timeline

Slip: about 2 years vs. the original date (given as a year)

  1. Announced28 Jul 2020
  2. Original date2023
  3. Last stated date2025

Change history

  • 17 Dec 2024status: cancelledOn 17 December 2024, Minister of State Assets Jakub Jaworowski announced the end of the Izera project. The brand was abandoned; ElectroMobility Poland's activity was redirected to a separate, successor project of a production-and-development hub in Jaworzno with partner Foxconn (Hon Hai) and a new brand (production planned around 2029).
  • 28 Jul 2020stage: announced

Significance

The closure of the Izera project meant that, after nearly a decade of work and more than PLN 580 million in public outlays, Poland gained neither its own electric car brand, nor a factory in Jaworzno, nor a finished vehicle. Public funds committed since 2016 did not translate into production, and the original deadlines for its launch (Q3 2023) were postponed multiple times. The experience and resources of ElectroMobility Poland were redirected towards a new model of cooperation with a foreign partner (Foxconn) in Jaworzno, constituting a separate, later undertaking.

Sources 9 · 6 independent · 9 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Wikipedia (pl)
    StatusInvestorStageAnnouncedOriginal dateLast stated date
    Status17 grudnia 2024 roku minister aktywów państwowych Jakub Jaworowski ogłosił koniec projektu Izera
    Investor19 października 2016 roku zainaugurowane zostało powstanie spółki akcyjnej ElectroMobility Poland
    Stage · AnnouncedOficjalna prezentacja marki Izera odbyła się 28 lipca 2020 roku
    Original dateprodukcja seryjna miała zostać rozpoczęta w III kwartale 2023 roku
    Last stated datewytwarzanie pierwszych sztuk miało rozpocząć się dwa lata później niż zakładano – w czwartym kwartale 2025 roku
    Locationw trzecim kwartale 2021 roku rozpocznie się budowa pierwszych zakładów produkcyjnych samochodów marki Izera, za której lokalizację obrano Jaworzno w województwie śląskim
  2. XYZ.pl
    CostDeliveryLosses
    Costtotal expenditures exceeded PLN 580 million (EUR 123 million) net
    DeliveryThe outcome: no car, no factory, and growing questions over whether the money has been well spent.
    LossesBetween 2018 and 2023, Poland’s state-controlled EV venture spent over PLN 580 million (EUR 123 million) on partners, including Chinese, Italian, and German firms.
  3. Money.pl12 Apr 2025
    Failure description
    Failure descriptionTomasz Kędzierski, prezes ElectroMobility Poland, ogłosił koniec Izery, ale nie koniec działalności spółki.
  4. OKO.press22 Apr 2025
  5. Interia Motoryzacja
    ScopeStatus
    ScopeTo koniec Izery. 4,5 mld zł na inną markę i fabrykę w Jaworznie
    StatusElectroMobility Poland kończy projekt samochodu Izera i skupia się na nowej europejskiej marce motoryzacyjnej realizowanej z partnerem globalnym.
  6. Najwyższa Izba Kontroli (NIK)20 Sep 2023I/22/002/KST
    FundingSchedule
    Fundingzaangażowanie przez Prezesa Rady Ministrów w II poł. 2021 r. kwoty 250 mln zł ze środków Funduszu Reprywatyzacji
    Schedulejuż według stanu na dzień 31 grudnia 2021 r. Projekt nie był realizowany zgodnie z harmonogramem
  7. OKO.press
  8. Money.pl19 Apr 2024
  9. Bankier.pl7 May 2026
    Scope
    ScopePartnerem strategicznym ElectroMobility Poland dla projektu budowy hubu elektromobilności w Jaworznie będzie tajwański koncern Foxconn
    ScopeZastrzegł jednak, że nie będzie to Izera.