🚆Transportstrategic

DCT Gdańsk Deepwater Container Terminal (Baltic Hub) – Terminal T1

completedstage: operational
USD 200 million
estimate · data from 2007net or gross: not recorded≈ PLN 800 million (value-by-stage, est., nominal)funding: private financeLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Poland's first deepwater container terminal, located within the Gdańsk seaport, in the outer port (part of the Northern Port). The terminal was created to receive deepwater, transoceanic container ships on the Baltic Sea. Work on the terminal began in October 2005, and the opening took place on 3 October 2007; the first ship called even before the official opening, on 1 June 2007. Under the first stage (T1) an artificially reclaimed pier of 25.2 ha (800 m long and 315 m wide) was created, on which 2 container-handling berths were built, thanks to a USD 200 million investment. The terminal operator was DCT Gdańsk S.A.; the entire shareholding package belonged at the time to the Australian investment fund Macquarie GIF II. In 2022 the terminal was renamed Baltic Hub.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Construction startOct 2005
  2. Delivery3 Oct 2007

Change history

  • 3 Oct 2007stage: operational
  • 1 Jun 2007stage: commissioning
  • Oct 2005stage: construction

Significance

DCT Gdańsk was Poland's first deepwater container terminal, able to receive deepwater, transoceanic container ships directly on the Baltic Sea, without the need for transshipment in Western European ports. Under the first stage (T1), on an artificially reclaimed pier of 25.2 ha (800 m long, 315 m wide), 2 container-handling berths were created, brought into service in 2007 thanks to a USD 200 million investment. The terminal, later renamed Baltic Hub, became the largest and most modern maritime container terminal in Poland.

Sources 4 · 3 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Wikipedia (pl)
    StatusStageConstruction startDeliveryStage historyCostInvestorFunding
    Status · Delivery · Stage historyOtwarcie nastąpiło 3 października 2007 roku.
    StageTerminal został utworzony, by na Morzu Bałtyckim przyjmować głębokowodne, transoceaniczne kontenerowce
    Construction start · Stage historyPrace nad terminalem rozpoczęły się w październiku 2005.
    Costna którym wybudowano 2 stanowiska do przeładunku kontenerów, dzięki inwestycji 200 mln dolarów
    InvestorDo tej pory całościowy pakiet udziałów należał do australijskiego funduszu inwestycyjnego Macquarie GIF II – jednego z trzech funduszy grupy Macquarie Group

    The sentence describes the company's owner up to the ownership change described in the same paragraph (2019), which covers the construction of terminal T1; the card gives the investor from the construction period.

    FundingDo tej pory całościowy pakiet udziałów należał do australijskiego funduszu inwestycyjnego Macquarie GIF II – jednego z trzech funduszy grupy Macquarie Group(inne języki), który inwestuje na całym świecie aktywa emerytów w infrastrukturę.
    Stage historyPierwszy statek zawinął jeszcze przed oficjalnym otwarciem terminala, 1 czerwca 2007
  2. PortalMorski.pl24 Oct 2012
  3. Encyklopedia Gdańska (gedanopedia.pl)
  4. Studia Maritima, Vol. 32 (Wydawnictwo Naukowe Uniwersytetu Szczecińskiego); A. Bartosiewicz2019