← all projects
🚆Transportstrategic

Construction of the Olsztyn tram network with a Solaris Tramino fleet (revival of trams)

completedstage: operationaldelivereddelayed
PLN 650 million
programme budget (multi-year) · data from 2015net or gross: not recorded≈ PLN 650 million (value-by-stage, est., nominal)funding: EU funds, local governmentLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The revival of tram transport in Olsztyn was carried out under the project 'Modernisation and development of the integrated public-transport system in Olsztyn', co-financed from the Operational Programme Development of Eastern Poland 2007–2013. Trams had run in the city from 1907 to 1965, and the system was reopened on 19 December 2015, when Line 1, Wysoka Brama – Kanta, was put into service; this was the only revived tram system in Poland. The project beneficiary was the Olsztyn Municipality, and its total value was PLN 650,136,059.57, of which EU co-financing reached PLN 384,788,279.51. The scope of the investment included the construction of about 17 km of new tram network, delivery of 15 Solaris Tramino trams (a contract of 21 September 2012 worth PLN 120.5 million gross), dedicated bus lanes and an intelligent transport system (ITS). Construction of the network formally began on 1 March 2012 (actually on 12 September 2012), and completion was originally planned for the turn of June and July 2014; construction of the new network was completed around the turn of October and November 2015. The original infrastructure contract with the FCC Construccion consortium (signed on 27 June 2011, worth approximately PLN 249.8 million) was terminated in August 2013, and the works were completed by, among others, Skanska, Strabag, Torpol, Balzola and Budimex.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[2]
Scheduledelayed[2]
Utilisationin use[4]

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

eksploatacja sieci tramwajowej
Current
system tramwajowy czynny i eksploatowany od 19 grudnia 2015 roku (2026)

Timeline

Slip: +17 mo. vs. the original date

  1. Construction start12 Sep 2012
  2. Original dateJul 2014
  3. Delivery19 Dec 2015

Significance

The launch of trams in Olsztyn on 19 December 2015 was the only revival of a tram system in Poland (trams had run there from 1907 to 1965) and the first construction of a new tram network in a Polish city in decades. The investment, carried out with substantial EU funding from the Operational Programme Development of Eastern Poland, gave the city a new backbone for public transport (about 17 km of network, 15 Solaris Tramino trams) and became a reference point for the network's later expansion, including towards the Jaroty and Pieczewo housing estates.

Sources 6 · 4 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Ministerstwo Funduszy i Polityki Regionalnej (mapadotacji.gov.pl)
    CostInvestorFunding
    Costwartość projektu 650 136 059,57 zł
    Investornazwa beneficjenta Gmina Olsztyn
    Fundingdofinansowanie z UE 384 788 279,51 zł
  2. Wikipedia (pl)
    StatusStageConstruction startOriginal dateDeliverySchedule
    Status · Stage · Deliverysystem komunikacji tramwajowej, działający w Olsztynie w latach 1907–1965 i ponownie od 19 grudnia 2015
    Construction startFormalnie budowę sieci rozpoczęto 1 marca 2012, a jej zakończenie przewidziane było na przełom czerwca i lipca 2014. Faktycznie budowa sieci tramwajowej rozpoczęła się 12 września 2012 roku
    Original dateFormalnie budowę sieci rozpoczęto 1 marca 2012, a jej zakończenie przewidziane było na przełom czerwca i lipca 2014.

    The source gives “the turn of June and July 2014”; the card reads a period as its last month (a date given as a period means its end).

    DeliveryBudowę nowej sieci zakończono na przełomie października i listopada 2015
    SchedulePierwotnie pojazdy miały zostać dostarczone między 31 marca i 14 sierpnia 2014, jednak w związku z opóźnieniem budowy linii dostawy przesunięto na okres od maja do września 2015.
  3. WNP.pl2012
  4. Urząd Miasta Olsztyna (olsztyn.eu)2025
    Utilisation
    UtilisationWiosną 2016 r. trzy linie tramwajowe przewoziły w dni robocze 18 841 pasażerów. Jesienią 2025 roku pięć linii obsługuje już 37 267 pasażerów dziennie.
  5. Funding
    FundingCałkowity koszt realizacji I etapu inwestycji (wraz z modernizacją ulic, budową ul. Obiegowej i buspasów) to 496 mln zł, z czego miasto przeznaczyło na ten cel poniżej 100 mln zł.