A1 Motorway Gdańsk–Toruń (Gdańsk Transport Company concession section)

completed stage: operational delivered
730 mln EUR
contract value · data from 2011 ≈ 3.1 bn PLN (value-by-stage, est., nominal) funding: PPP (private financing by the concessionaire)

The northern, concession section of the A1 motorway, approximately 152 km long, running from Gdańsk (Rusocin) to Toruń, delivered under a public-private partnership formula by Gdańsk Transport Company S.A., which financed, designed, built, and operates the route (ultimately through 2039). The concession agreement with the government was signed in August 2004. The investment was carried out in two stages: Stage I Rusocin–Nowe Marzy (90 km, contract value EUR 529 million), whose first sections opened on 22 December 2007, and Stage II Nowe Marzy–Toruń (62 km, contract value EUR 730 million, including EUR 581 million for the road and EUR 149 million for bridge structures). Stage II was opened to traffic on 14 October 2011, completing the continuous motorway connection Gdańsk–Toruń ahead of the UEFA Euro 2012 European football championship. The figure in the cost field (EUR 730 million) refers to the Stage II contract (Nowe Marzy–Toruń), opened in 2011.

How it went

Assessment: settled. Signals only where documented.

Delivery delivered
Schedule ahead of schedule
Utilisation in use
Scope as announced

Timeline

  1. Announced Aug 2004
  2. Delivery 14 Oct 2011

Change history

  • 14 Oct 2011 status: completed The opening to traffic of stage II (Nowe Marzy–Toruń) completed the concession section Gdańsk–Toruń.
  • 14 Oct 2011 stage: operational

Significance

The completion in 2011 of the concession section Gdańsk–Toruń provided the first continuous motorway connection between the Tricity area and central Poland and shortened travel time between Gdańsk and Toruń to approximately 65 minutes. The route was one of the largest road investments delivered in Poland under a public-private partnership formula, and its completion ahead of UEFA Euro 2012 was significant for handling traffic for the tournament co-hosted by Poland. The concessionaire Gdańsk Transport Company S.A. manages the entire approximately 152 km section as a toll road until 2039, after which the facility is to be transferred to the public side.

Sources 5

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. AmberOne / Gdańsk Transport Company Oct 2011
    StatusStageDeliveryCostOutcome
    Status „W dniu 14 października 2011 roku, zostają oddane do użytku kolejne 62 kilometry"
    Stage „Oddanie do eksploatacji drugiego etapu, prowadzonej przez nas inwestycji zakończyło ostatecznie realizację koncesyjnego odcinka autostrady A1"
    Cost „Cena budowy drugiego etapu inwestycji wyniosła 730 mln EUR, w tym 581 mln EUR/droga i 149 mln EUR/mosty"
  2. NDI
    CostInvestorSchedule
    Schedule „4,5 miesiąca przed terminem"
  3. Wikipedia (pl)
    InvestorAnnouncedDeliveryStage historyStatusStatus history
    Announced „sierpień 2004 – podpisanie Umowy Koncesyjnej Etap 1"
    Delivery „14 października 2011 – oddanie do ruchu Etapu 2"
  4. Wikipedia (pl)
    StageCost
  5. TerenyInwestycyjne.info Oct 2011
    DeliverySignificance
    Investor „Gdańsk Transport Company - spółka posiadająca koncesję na finansowanie, projektowanie, budowę oraz eksploatację tego fragmentu autostrady"
    locations „partner prywatny będzie zarządzać całym 152-km odcinkiem autostrady, aż do roku 2039"