A1 motorway Częstochowa – Pyrzowice

completedstage: operationaldelivered
PLN 3.0 billion
programme budget (multi-year) · data from 2019net or gross: not recorded≈ PLN 3.0 billion (value-by-stage, est., nominal)funding: EU fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Construction of the Silesian section of the A1 motorway from the Pyrzowice interchange (near Katowice Airport) to the Częstochowa Północ interchange, together with the Częstochowa motorway bypass, with a total length of approximately 57.70 km. The project was carried out by the General Directorate for National Roads and Motorways (GDDKiA), which divided it into four sections (F: Częstochowa Północ – Blachownia, G: Blachownia – Zawodzie/Częstochowa Południe, H: Częstochowa Południe – Woźniki, I: Woźniki – Pyrzowice) under a "design and build" system. Contracts with contractors were signed in 2015-2016 (including the contract for section F with the Salini company on 12 October 2015). On 2 August 2019 a 33-kilometre stretch from the Pyrzowice interchange to the Częstochowa Blachownia interchange was opened to traffic (sections G, H, I), and on 23 December 2019 the last, approximately 20-kilometre section F (Częstochowa Północ – Blachownia) was opened, closing the route along its full length. The investment was worth approximately PLN 3.0 billion, of which approximately PLN 1.35 billion was co-financing from the EU Cohesion Fund under the Operational Programme Infrastructure and Environment 2014-2020.

How it went

Assessment: settled, as of 23 Dec 2019. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[3]

Timeline

  1. Construction start2015
  2. Delivery2019

Change history

  • 23 Dec 2019stage: operational

Significance

The Częstochowa – Pyrzowice section closed the A1 motorway in Silesia, connecting the Częstochowa motorway bypass with the existing A1 route near Pyrzowice and Katowice Airport. Together with the concurrently built Tuszyn – Częstochowa section, it created a continuous north-south motorway corridor (part of the TEN-T network) running from the Tricity towards the border with the Czech Republic. The investment, worth approximately PLN 3.0 billion, with EU co-financing of around PLN 1.35 billion, was one of the largest road projects opened to traffic in Poland in 2019.

Sources 5 · 4 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Infrastruktury (gov.pl)2 Aug 2019
    StageCost
    StageOd 2 sierpnia 2019 r. kierowcy mogą już korzystać z kolejnych 33 km
    CostInwestycja o wartości 3,014 mld zł
  2. Mapa Dotacji UE (gov.pl)
    Investor
    Investornazwa beneficjenta GENERALNA DYREKCJA DRÓG KRAJOWYCH I AUTOSTRAD
  3. Generalna Dyrekcja Dróg Krajowych i Autostrad (serwis archiwalny)23 Dec 2019
    StatusConstruction startDelivery
    Status · Delivery23 grudnia 2019 r. - udostępnienie ciągu głównego do ruchu
    Construction start12 października 2015 r. - podpisanie umowy na zaprojektowanie i wybudowanie odcinka F autostrady A1 z firmą Salini
  4. Funding
    FundingMaksymalna kwota dofinansowania z UE: 1 329 654 737,61 PLN