Wrocław – Tramwaj Plus Programme (Integrated Rail Transport System in the Agglomeration and in Wrocław – Stage I)

completedstage: operationaldelivered
PLN 736 million
programme budget (multi-year) · data from 2012net or gross: not recorded≈ PLN 736 million (value-by-stage, est., nominal)funding: EU funds, local governmentLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Tramwaj Plus was a Wrocław programme for developing fast tram services, carried out by the Municipality of Wrocław as the EU project 'Integrated Rail Transport System in the Agglomeration and in Wrocław – Stage I', co-financed from the Operational Programme Infrastructure and Environment. The total value of the Stage I project was PLN 736,189,291.52, of which EU co-financing accounted for PLN 477,747,653.84; the co-financing agreement (POIS.07.03.00-00-006/10-00) was signed on 6 March 2012, and the implementation period covered 2006–2013. Earlier, in 2007, the cost of the programme's tasks was estimated in the media at approximately PLN 700 million, and in 2008 (including the purchase of rolling stock) at approximately PLN 800 million; the investment was carried out by the municipal company Wrocławskie Inwestycje sp. z o.o. The project built 5.3 km of new track and rebuilt 37.85 km of existing track, and purchased 39 low-floor rolling stock units, including bidirectional Škoda 19T trams serving lines 31, 32 and 33, which were marked with the 'PLUS' suffix. Ahead of the Euro 2012 finals, the new tracks connected the Gaj and Kozanów housing estates with the city centre: the Gaj branch was put into service on 11 September 2011, and the line to Kozanów (with branches to Kozanów and Stadion Wrocław) on 31 March 2012. The plans for tram priority (an ITS system) were not fully implemented, and on 17 February 2014 the 'PLUS' suffix was removed from the markings of lines 31, 32 and 33. The infrastructure built remains in operation as part of Wrocław's tram network.

How it went

Assessment: settled, as of 17 Feb 2014. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[5]
Utilisationin use[5]

Timeline

  1. Announced2007
  2. Original date2011
  3. Delivery2012

Significance

Tramwaj Plus was one of the largest urban transport development projects in Wrocław during preparations for Euro 2012, and it introduced to the city, for the first time, the concept of fast tram lines given their own designation and served by new, bidirectional rolling stock. The new tracks permanently connected the large Gaj and Kozanów housing estates with the city centre. At the same time, the programme showed the limits of the solutions available at the time: the ITS priority system did not work as intended, and the promise of noticeably faster journeys was not kept, which led to the removal of the 'PLUS' brand from lines 31, 32 and 33 in February 2014. The infrastructure built nonetheless remains in operation as part of Wrocław's tram network.

Sources 6 · 6 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Biuletyn Informacji Publicznej Urzędu Miejskiego Wrocławia
    CostFunding
    CostCałkowita wartość projektu: 736 189 291,52 PLN
    FundingWkład Miasta: 258 441 637,68 PLN
  2. Ministerstwo Funduszy i Polityki Regionalnej (mapadotacji.gov.pl)
    Funding
    Fundingdofinansowanie z UE 477 747 653,84 zł
  3. Rynek Kolejowy18 Jul 2007
    AnnouncedOriginal date
    AnnouncedKoszt realizacji tych zadań szacujemy na 700 mln zł
    Original datePrace mają się zakończyć najpóźniej do 2011 roku
  4. wroclawskakomunikacja.pl26 Jan 2011
    Investor
    Investormówi Marek Szempliński ze spółki Wrocławskie Inwestycje, która odpowiada za przebudowę dróg i torów wokół powstającego na Euro stadionu.
  5. Prywatna Strona Miłośnika Komunikacji Miejskiej i Szynowej
    StatusDeliveryUtilisation
    Status · DeliveryPół roku później, 31 marca 2012 roku, do użytku oddano linię tramwajową na Kozanów, która pod koniec swojej trasy rozdziela się na dwa odcinki zakończone końcówkami Kozanów (Dokerska) oraz Stadion Wrocław (Królewiecka).
    DeliveryPół roku później, 31 marca 2012 roku, do użytku oddano linię tramwajową na Kozanów
    Utilisation31 PLUS kursuje na trasie Stadion Wrocław (Królewiecka) - Gaj co 12 minut w godzinach szczytu. 32 PLUS kursuje po trasie Kozanów (Dokerska) - Gaj również z częstotliwością co 12 minut.
  6. wroclaw.pl (Urząd Miejski Wrocławia)18 Feb 2014
    Stage
    StageLinie tramwaju połączyły duże wrocławskie osiedla Kozanów i Gaj z centrum miasta