Volkswagen Motor Polska – Diesel Engine Plant in Polkowice

completedstage: operationaldelivered
PLN 917 million
estimate · data from 2001net or gross: not recorded≈ PLN 917 million (value-by-stage, est., nominal)funding: private financeThe source gives EUR 250 million. The zloty figure is our conversion at the rate for 2001, so the site fixed rate will not reproduce it.Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Volkswagen Group's diesel engine plant in Polkowice, Lower Silesia, was one of the largest foreign direct investments made in the 1990s in the sub-zone of the Legnica Special Economic Zone. The company Volkswagen Motor Polska was established on 13 May 1998, and the foundation stone for the plant was laid on 16 September 1998. The plant was officially opened on 25 August 1999 by Dr Ferdinand Piëch, then Chairman of the Board of Management of Volkswagen AG. The plant initially produced 1.9 TDI diesel engines with pump-injection units; by the end of 2001 capital expenditure had reached approximately EUR 250 million, the company employed 800 people and produced 540,000 engines a year. In subsequent years the plant expanded further (common rail engines from 2008, EURO 6-compliant MDB modular engines from 2013), supplying the Volkswagen, Audi, SEAT and Škoda brands; total investment in the Polkowice plant was estimated at approximately EUR 370 million (as of 2020). The plant is owned by Volkswagen Motor Polska Sp. z o.o., part of the Volkswagen AG group.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[2]
Utilisationin use[5]
roczna produkcja silników wysokoprężnych
Current
ok. 540 000 silników rocznie (2001); ponad 600 tys. silników rocznie; 10-milionowy silnik w 2016 r., 14-milionowy w 2023 r. (2001–2023)
Unit
silniki/rok

Timeline

  1. Announced13 May 1998
  2. Construction start16 Sep 1998
  3. Delivery25 Aug 1999

Significance

The Volkswagen engine plant in Polkowice was one of the largest foreign direct investments made in the 1990s in the sub-zone of the Legnica Special Economic Zone, and a major employer in Lower Silesia. The plant supplies diesel engines to Volkswagen Group brands (Volkswagen, Audi, SEAT, Škoda); in December 2016 it produced its 10 millionth engine, and in 2023, to mark the company's 25th anniversary, its 14 millionth engine.

Sources 5 · 4 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Volkswagen Motor Polska Sp. z o.o.
    StatusCost
    StatusW sierpniu fabrykę silników w Polkowicach oficjalnie otwiera dr Ferdinand Piech, ówczesny prezes zarządu koncernu Volkswagen
    Costinwestycje sięgają ok. 250 milionów euro, firma zatrudnia 800 osób i produkuje 540 000 silników wysokoprężnych 1,9 TDI
  2. businesspl.com22 Apr 2020
    StageAnnouncedConstruction startDeliveryFunding
    StageAktualnie produkuje on ponad 600 tys. silników rocznie.
    AnnouncedSpółka Volkswagen Motor Polska powstała 13 maja 1998 roku
    Construction startpo pół roku od położenia kamienia węgielnego (16 września 1998 roku)
    Delivery25 sierpnia 1999 roku, miało miejsce oficjalne otwarcie fabryki
    FundingZarząd Koncernu Volkswagen postanowił, że nowoczesna fabryka Volkswagen Motor Polska zostanie zbudowana w Polkowicach, na terenie Legnickiej Specjalnej Strefy Ekonomicznej
  3. Wikipedia (pl)
    Investor
    InvestorVolkswagen Motor Polska – producent silników samochodowych z siedzibą w Polkowicach na Dolnym Śląsku, powstały w 1999 r. w podstrefie Legnickiej Specjalnej Strefy Ekonomicznej, należy do koncernu Volkswagen AG.
  4. Legnicka Specjalna Strefa Ekonomiczna S.A.4 Sep 2023
    StatusStage
    Status · StageVolkswagen Motor Polska od 1998 roku nieustannie się rozwija oraz wdraża innowacyjne rozwiązania w produkcji wysokoprężnych jednostek napędowych o najnowocześniejszej konstrukcji na wielką skalę.
  5. Bankier.pl (aut. Marcin Kaźmierczak)28 Jul 2021
    StatusStageUtilisation
    Status · Stage · UtilisationPolkowicka fabryka Volkswagena produkuje silniki wysokoprężne już od 20 lat.