Łagiewnicka Route in Kraków (road with tram line)

completedstage: operational
PLN 840 million
programme budget (multi-year) · data from 27 Aug 2022net or gross: not recorded≈ PLN 840 million (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The Łagiewnicka Route is a 3.5 km stretch of Kraków's third ring road, with about 2 km in tunnels, five interchanges and a 1.7 km tram line from Kurdwanów. Construction began in February 2018 and the route opened on 27 August 2022, less than six months after the planned March 2022 date. The contractor was the Budimex and Ferrovial Agroman consortium. The total value of the investment was PLN 840 million, financed by loans from PFR, BGK and the European Investment Bank and by EU Cohesion Fund money.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, one carries no assessment yet, 3 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Construction startFeb 2018
  2. Original dateMar 2022
  3. Delivery27 Aug 2022

Significance

The route links Kurdwanów and Ruczaj bypassing the centre, relieves the Łagiewniki junctions and the Mateczny roundabout, and cuts tram journey times by 10–15 minutes on some routes. Sources attribute the delay to the pandemic and heavy rain.

Sources 3 · 3 independent

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Gmina Miejska Kraków11 Sep 2022
    CostDeliveryInvestor
    CostCałkowita wartość inwestycji wyniosła 840 milionów złotych
    DeliveryW sobotę, 27 sierpnia, po czterech latach budowy oddana została do użytku Trasa Łagiewnicka
    InvestorMariusz Piątkowski, prezes spółki Trasa Łagiewnicka SA
  2. Radio Kraków27 Aug 2022
    StatusStageConstruction startOriginal date
    Status · StageW Krakowie po czterech latach budowy oddano do użytku Trasę Łagiewnicką.
    Construction startJej budowa wraz z linią tramwajową rozpoczęła się w lutym 2018 r.
    Original dateZgodnie z planami całość miała być gotowa w marcu br.
  3. Ministerstwo Funduszy i Polityki Regionalnej27 Aug 2022