Sharp LCD module factory in Łysomice near Toruń (Sharp Manufacturing Poland, Pomorska SEZ Ostaszewo)

completedstage: operational
PLN 595 million
estimate · data from 2006net or gross: not recorded≈ PLN 595 million (value-by-stage, est., nominal)funding: state funds, private financeLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The Sharp Manufacturing Poland sp. z o.o. plant in Łysomice (Ostaszewo) near Toruń, in the Pomorska Special Economic Zone, was the Japanese Sharp group's first investment in Poland and its first factory in Europe. The investment was estimated at PLN 595 million. The factory started producing LCD modules for LCD televisions in January 2007; it was designed to produce around 10 million LCD modules a year and to employ at least 3,000 people once fully operational. The plant became the nucleus of a television-production cluster near Toruń (the Sharp/Orion park), attracting subcontractors and suppliers.

How it went

No outcome assessment: this record carries none on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.

Timeline

  1. Announced2006
  2. Delivery2007

Significance

The Sharp factory in Łysomice was Sharp's first investment in Poland and the group's first plant in Europe, starting the production of LCD modules for televisions in the Pomorska Special Economic Zone. It initiated a cluster of television and electronics production near Toruń (the Sharp/Orion park), attracting further investors and suppliers and creating at least 3,000 jobs once fully operational.

Sources 4 · 4 independent · 2 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. eGospodarka.pl7 Sep 2006
    CostAnnouncedInvestor
    CostDzięki nowej inwestycji, szacowanej na 595 mln zł, zatrudnienie znajdzie co najmniej 3 tys. osób.
    AnnouncedFabryka Sharpa w Łysomicach ma rozpocząć działalność jeszcze w tym roku
    InvestorToshiyuki Tajima - prezes zarządu Sharp Manufacturing Poland sp. z o.o.
  2. muratorplus.pl2006
    Funding
    FundingWartość pierwszego etapu inwestycji Sharpa osiągnie 44 mln euro.
  3. Sharp Corporation
    StatusStageDelivery
    Status · Stage · DeliverySMPL began production of LCD modules for LCD TVs in January 2007.
  4. Funding
    Funding€48.3 million of aid which the Polish authorities intend to grant to Sharp Manufacturing Poland