Saule Technologies (commercialization of perovskite solar cells)

cancelledabandonedwritten off
funding: private finance, EU funds, other sources

Saule Technologies is a Polish deep-tech company founded in 2014 around the inkjet-printing method for flexible, ultra-thin perovskite photovoltaic cells invented by Olga Malinkiewicz. The project's goal was the mass commercialization of this technology and the launch of a factory; in practice, only a pilot production line operated in Wrocław rather than a full-scale plant. The main strategic investor was the listed company Columbus Energy. Despite more than PLN 270 million in financing from public and private investors, the company did not achieve profitability – for 2024 it reported a net loss of PLN 65.8 million against revenues of PLN 1.27 million. In 2025 a sharp shareholder dispute broke out: in May 2025 the supervisory board removed co-founder Olga Malinkiewicz from the management board, notifications were filed with the prosecutor's office, and share trading was suspended in June 2025. On 26 June 2026 the shares were ultimately delisted from the NewConnect market due to the failure to submit financial reports for 2024 and 2025. The company found itself on the brink of bankruptcy and – according to reports – will most likely be placed into bankruptcy or restructuring; no formal bankruptcy has been declared, and the mass commercialization of perovskites has not yet been achieved.

Why it failed

The company did not achieve mass commercialization of perovskite technology nor launch the planned factory – only a pilot production line operated in Wrocław. For 2024 Saule Technologies reported a net loss of PLN 65.8 million against revenues of PLN 1.27 million. In May 2025 the supervisory board removed co-founder Olga Malinkiewicz from the management board, and a dispute among shareholders led to notifications being filed with the prosecutor's office. Share trading was suspended in June 2025, and on 26 June 2026 the shares were delisted from the NewConnect market due to the failure to submit financial reports for 2024 and 2025. The company found itself on the brink of bankruptcy and – according to media reports – will most likely be placed into bankruptcy or restructuring; no formal bankruptcy has been declared.

How it went

Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverynot delivered[7]
Utilisationnot operational[7]
Lossesknown sunk cost · PLN 250 million[7]

Timeline

  1. Construction start2014

Significance

Saule Technologies was the flagship Polish venture in perovskite photovoltaics and one of the most recognizable domestic deep-tech projects, based on the internationally acclaimed cell-printing method developed by Olga Malinkiewicz. The aspiration was for Poland to be the first in the world to mass-commercialize perovskite solar cells. Despite more than PLN 270 million in public and private financing gathered over a decade (from 2014), the project did not move from pilot to industrial scale – no factory was built, and the company found itself on the brink of bankruptcy and was delisted from the stock exchange. It is one of the most significant Polish examples of the difficulty of turning a breakthrough laboratory technology into a profitable industrial business.

Sources 10 · 9 independent · 10 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. money.plJun 2026
    Failure description
    Failure descriptionobrót akcjami Saule był zawieszony już od czerwca 2025 r.
    Failure descriptionrada nadzorcza odwołała Olgę Malinkiewicz z zarządu
  2. orestrukturyzacji.pl10 Jul 2025
  3. Gramwzielone.pl
    InvestorFailure description
    InvestorOlga Malinkiewicz, wiceprezes Saule SA oraz największy akcjonariusz Saule Technologies SA, złożyła zawiadomienie do Prokuratury Krajowej w Warszawie.
    LocationPilotażowa linia produkcyjna została uruchomiona przez Saule w zakładzie we Wrocławiu kilka lat temu
    Failure descriptionDotyczy ono podejrzenia działania na szkodę spółek Saule SA oraz Saule Technologies SA.
    Failure descriptionw czwartym kwartale 2024 r. – spółka miała 17,8 mln zł straty netto, co zwiększyło stratę za cały zeszły rok do 65,8 mln zł.
  4. Bankier.pl
  5. enerad.pl
  6. wnp.pl
    Failure descriptionAssessmentFunding
    Failure description · Assessmentspółka znajduje się dziś w bardzo trudnej sytuacji i najprawdopodobniej zostanie postawiona w stan upadłości lub restrukturyzacji
    Failure description · Fundingdo Saule Technologies wpłynęło ponad 270 mln zł - w tym ponad 100 mln zł od inwestorów prywatnych (Columbus, polskiej spółki DC24, i japońskiej grupy HIS) oraz pozostała część ze środków publicznych
  7. enerad.pl
    Failure descriptionDeliveryUtilisationLossesStatus
    Failure descriptionW 2024 roku Saule osiągnęło 1,27 mln zł przychodów, notując stratę netto na poziomie 65,79 mln zł.
    Delivery · UtilisationSaule Technologies nie rozpoczęło budowy fabryki modułów perowskitowych z powodu niewywiązania się inwestora z kluczowego zobowiązania finansowego.
    LossesNa rozwój i budowę pilotażowej fabryki wydano około 250 mln zł, z czego jedynie 60 mln zł pochodziło ze środków publicznych.
    StatusNowe kierownictwo zamknęło fabrykę i rozpoczęło przygotowania do sprzedaży firmy.
  8. Saule Technologies
  9. Perovskite-Info
    Construction start
    Construction startSaule Technologies has been working on the application of ink-jet printing for fabricating free-form perovskite solar modules since 2014.
  10. Funding
    FundingSaule Technologies od początku korzystało ze wsparcia publicznego: pozyskało ogromne środki z grantów Unii Europejskiej (22 mln zł) oraz Narodowego Centrum Badań i Rozwoju NCBR (25 mln zł).