🚆Transportstrategic

S8 Expressway Jeżewo – Białystok (to the Choroszcz interchange)

completedstage: operationaldelivered
PLN 675 million
contract value · data from 2009net or gross: not recorded≈ PLN 675 million (value-by-stage, est., nominal)funding: EU funds, state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Upgrade of national road no. 8 to S8 expressway standard on a 24.5 km section from the Jeżewo interchange to Białystok (to the Choroszcz interchange) in the Podlaskie voivodeship. The project by the General Directorate for National Roads and Motorways (GDDKiA) was carried out under a 'design and build' formula by the consortium of Mota-Engil Polska S.A., Strabag sp. z o.o. and Transprojekt Gdańsk. The construction works contract was worth PLN 675 million, and the total project cost (including land purchases, documentation and archaeological works) reached PLN 900 million, of which PLN 528 million came from co-financing under the Operational Programme Infrastructure and Environment. Construction started on 20 October 2010, and the section, with two carriageways of two lanes each way and the Jeżewo, Rzędziany, Tykocin and Choroszcz interchanges, was opened to traffic on 12 September 2012. It was the largest road project in the Podlaskie region.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[1]
Utilisationin use[4]
odcinek drogi ekspresowej w eksploatacji
Current
24,5 km oddane do ruchu 12 września 2012, dwie jezdnie po dwa pasy w każdą stronę

Timeline

  1. Announced2009
  2. Construction start20 Oct 2010
  3. Delivery12 Sep 2012

Significance

The opening of the 24.5 km Jeżewo – Białystok S8 section to traffic on 12 September 2012 significantly improved the connection between Białystok, the whole Podlaskie region and central Poland, creating a direct dual-carriageway, expressway-standard connection along national road no. 8 (Warsaw – Białystok). The project, described as the largest road investment in the Podlaskie region, took transit traffic out of neighbouring towns thanks to the Jeżewo, Rzędziany, Tykocin and Choroszcz interchanges.

Sources 7 · 4 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Generalna Dyrekcja Dróg Krajowych i Autostrad (GDDKiA)2012
    StatusStageAnnouncedDelivery
    Status · Stage · DeliveryOd 12 września 2012 na 24,5 km odcinku Jeżewo-Białystok kierowcy mają do dyspozycji po dwa pasy ruchu w każdą stronę
    AnnouncedRozbudowa drogi krajowej nr 8 do parametrów drogi ekspresowej na odcinku Jeżewo -Białystok rozpoczęła się w 2009 roku – umowa na zrealizowanie inwestycji w systemie ”Zaprojektuj i zbuduj” podpisana została 12 sierpnia.
  2. Generalna Dyrekcja Dróg Krajowych i Autostrad (GDDKiA)22 Oct 2010
    Construction start
    Construction startW dniu 20 października, rozpoczęła się budowa drogi ekspresowej S8

    year taken from the source's publication date (22 Oct 2010)

  3. Inżynier Budownictwa2009
    CostInvestorFunding
    CostKontrakt na roboty budowlane jest wart 675 mln zł.
    InvestorPrzedstawiciele Generalnej Dyrekcji Dróg Krajowych i Autostrad podpisali umowę na zaprojektowanie i zbudowanie 24,5-kilometrowego odcinka S8 z konsorcjum firm: Mota – Engil Polska S.A., Strabag sp. z o.o. oraz Transprojekt Gdańsk.
    FundingBędzie finansowany w 85 procentach przez unijny Program Infrastruktura i Środowisko.
    FundingBędzie finansowany w 85 procentach przez unijny Program Infrastruktura i Środowisko. Resztę dopłaci budżet państwa.
  4. Inżynier Budownictwa2012
    Utilisation
    UtilisationNa odcinku Jeżewo-Białystok kierowcy mają już do dyspozycji po dwa pasy ruchu w każdą stronę. Obok jezdni głównej, ruch odbywa się także na drogach serwisowych i drodze autobusowej.
  5. Wikipedia (pl)
  6. Bankier.pl12 Aug 2009
    CostInvestor
    Cost · Investor12.08. Białystok (PAP) - 675 mln zł będzie kosztowało zaprojektowanie i budowa fragmentu drogi S8 Białystok-Jeżewo w kierunku Warszawy. Generalna Dyrekcja Dróg Krajowych i Autostrad (GDDKiA) oraz polsko-portugalskie konsorcjum firm, które wygrało przetarg, podpisały w środę w Białymstoku umowę w tej sprawie.