S6 completion: Koszalin – Słupsk – Bożepole Wielkie

completed stage: operational delivereddelayed
2.9 bn PLN
programme budget (multi-year) · data from Jun 2026 ≈ 2.9 bn PLN (value-by-stage, est., nominal) funding: state budget, EU – FEnIKS programme (over PLN 1.4 billion, Słupsk – Bożepole Wielkie section)

A programme to close the S6 expressway along the Baltic coast on the section from Koszalin through Słupsk to the Bożepole Wielkie interchange, carried out by GDDKiA. The Koszalin – Słupsk stretch (46 km, eight interchanges and 48 bridge structures) was officially opened to traffic on 22 December 2025. On the further Słupsk – Bożepole Wielkie section, traffic was launched in stages: the 22 km Leśnice – Bożepole Wielkie stretch was made available on 29 April 2026, and the last sections between Słupsk and Leśnice (over 40 km) were opened on 26 June 2026, closing the over-300 km expressway route from Szczecin to the Tri-City. The entire Słupsk – Bożepole Wielkie investment was co-financed from EU funds under the FEnIKS programme.

How it went

Assessment: provisional. Signals only where documented.

Delivery delivered
Schedule delayed
Utilisation too early
Scope as announced

Timeline

Slip: +3 mo. vs. the original date

  1. Original date 9 Apr 2026
  2. Current date 26 Jun 2026
  3. Delivery 26 Jun 2026

Change history

  • 26 Jun 2026 stage: operational
  • 22 Dec 2025 stage: operational

Significance

The opening of the further S6 sections closed the over-300 km expressway corridor running along the Polish coast, providing an uninterrupted expressway connection between Szczecin and the Tri-City. According to GDDKiA, travel time between Gdańsk and Szczecin was shortened by about 1.5 hours – from about five to about 3.5 hours. The Koszalin – Słupsk stretch alone is 46 km of route with eight interchanges and 48 bridge structures, and the entire Słupsk – Bożepole Wielkie section was delivered with EU funding support exceeding PLN 1.4 billion.

Sources 5 · 3 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. Radio Gdańsk 22 Dec 2025
    Stage historyOriginal dateCostDescriptionSignificance
    stage_events[0].date „Droga S6 z Koszalina do Słupska została oficjalnie otwarta"
    Original date „Planowany termin zakończenia budowy całej drogi ekspresowej to 9 kwietnia 2026 roku"
  2. PortalSamorzadowy.pl 24 Jun 2026
    StatusStageStage historyDeliveryInvestorDescription
    Status „26 czerwca zostanie otwarta droga ekspresowa S6"
    Investor „Generalna Dyrekcja Dróg Krajowych i Autostrad"
    locations[2] „22-kilometrowy odcinek Leśnice-Bożepole Wielkie"
    Scope „pełne 300 km ekspresowej jazdy nad morzem"
  3. Ministerstwo Infrastruktury (gov.pl) 24 Jun 2026
    CostScheduleSignificanceDescription
    Cost „Wartość całej inwestycji to niemal 2,9 mld zł, a dofinansowanie z UE wyniosło ponad 1,4 mld zł"
  4. GDDKiA / wykonawca (serwis inwestycji)
    Investor
  5. zblizenia.pl
    OutcomeOriginal dateSchedule
    Schedule „Termin oddania odcinka trasy przesunięto na 2026 rok, powodem opóźnienia są problemy, na jakie natrafili wykonawcy inwestycji. W związku z roszczeniami pogodowymi (za lata 2023-2024) oraz problemami z nielegalnymi wysypiskami śmieci"