Completion of the 22.4 km S5 expressway section between the Świecie Południe (Dworzysko) and Bydgoszcz Północ (Aleksandrowo) junctions. GDDKiA withdrew from its contracts with Impresa Pizzarotti on 11 June 2019 and on 24 April 2020 signed a contract with the PBDiM Kobylarnia (leader) and Mirbud consortium, with a contract value of PLN 583,377,261. The contract covered a 2x2 dual carriageway with space reserved for a third lane and the Gruczno, Pruszcz, Trzeciewiec and Bydgoszcz Północ interchanges. Since the night of 21 to 22 October 2022 the whole section has been passable in the full 2x2 cross-section.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section
Timeline
- DeliveryOct 2022
Significance
The section completes the dual carriageway S5 north of Bydgoszcz. Metropolia Bydgoska describes the S5 construction as three years late.
Sources 3 · 3 independent
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Inżynier Budownictwa24 Apr 2020CostInvestor
CostKoszt inwestycji wyniesie 583 377 261 zł.
InvestorGDDKiA podpisała umowę na dokończenie budowy drogi ekspresowej S5 Świecie Południe–Bydgoszcz Północ.
- Metropolia Bydgoska21 Oct 2022StatusStageDeliverySignificance
Status · Stage · DeliveryPrace zakończyły się w nocy z piątku na sobotę – od teraz S5 w pełnym przekroju 2×2 jest przejezdna na całej długości.
SignificanceBudowa drogi ekspresowej S5 – choć z trzyletnim opóźnieniem – zbliża się do szczęśliwego finału.
- Conadrogach.pl24 Apr 2020