🚆Transportstrategic

S3 Bolków – Kamienna Góra with the TS-26 tunnel (S3 Legnica–Lubawka)

completed stage: operational delivereddelayed
1.8 bn PLN
programme budget (multi-year) · data from Jul 2024 ≈ 1.8 bn PLN (value-by-stage, est., nominal) funding: state budget, EU – Infrastructure and Environment Operational Programme (approx. PLN 928 million)

Construction of an approx. 16 km mountain section of the S3 expressway, Bolków – Kamienna Góra, in Lower Silesia, forming part of the S3 Legnica (A4) – Lubawka task that closes the Polish part of the S3 corridor toward the border with the Czech Republic. The route was led through the ranges of the Sudetes with numerous engineering structures, including two twin-bore tunnels: TS-26, approx. 2,300 m long – the longest non-urban tunnel bored in rock in Poland – and TS-32, approx. 320 m long. GDDKiA's Wrocław branch signed the design-and-build contract in October 2018, and boring of the TS-26 tunnel was carried out from December 2020 to February 2022. The contractor was a consortium of PORR (leader) and PORR Bau GmbH. The section was opened to traffic on 31 July 2024. The value of the investment came to over PLN 1,785 million, of which approx. PLN 928 million was funding from the EU Operational Programme Infrastructure and Environment.

How it went

Assessment: settled. Signals only where documented.

Delivery delivered
Schedule delayed
Utilisation in use
Scope as announced
vehicle trips in the first year of operation (AADT approx. 6,3 thousand/day)
23 / 0 vehicles (2024-07-31 to 2025-07)

Timeline

Slip: +2 mo. vs. the original date

  1. Construction start Oct 2018
  2. Original date May 2024
  3. Current date Jul 2024
  4. Delivery 31 Jul 2024

Change history

  • 31 Jul 2024 stage: operational

Significance

The Bolków – Kamienna Góra section closed the Polish part of the S3 expressway in the Sudetes, providing a continuous expressway connection along the north–south corridor from the Baltic coast toward the border with the Czech Republic. The key element of the route is the twin-bore TS-26 tunnel, approx. 2,300 m long – the longest non-urban tunnel bored in rock in Poland – which, together with the shorter TS-32 tunnel and numerous viaducts, enabled the road to be carried through difficult mountain terrain. The investment, worth over PLN 1,785 million and co-financed from EU funds with approx. PLN 928 million, improved transport accessibility in Lower Silesia and strengthened the cross-border transport corridor of the TEN-T network.

Sources 7 · 4 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. Ministerstwo Infrastruktury (gov.pl) 31 Jul 2024
    StatusStageStage historyDeliveryCostcost.fundingInvestorDescriptionSignificance
    Status „Droga ekspresowa S3 Bolków – Kamienna Góra oddana do ruchu"
    cost.funding „Unijne dofinansowanie tej inwestycji w ramach Programu Operacyjnego Infrastruktura i Środowisko wyniosło ok. 928 mln zł"
    Investor „Generalna Dyrekcja Dróg Krajowych i Autostrad"
    locations[0].voivodeship „Cała S3 na terenie Dolnego Śląska S3 będzie miała 135 km długości"
  2. Money.pl 31 Jul 2024
    Construction startCostDescription
    stage_events[0] „Wrocławski oddział GDDKiA w środę (31 lipca) otworzy drogę ekspresową z Bolkowa do Kamiennej Góry"
    Construction start „Umowę na jego projekt i budowę GDDKiA oddział Wrocław podpisał w październiku 2018 r."
    Cost „Koszt inwestycji to 1 mld 785 mln zł"
    locations[1].voivodeship „droga ekspresowa S3 w środę oficjalnie wydłuży się o 16 km, bo taka jest długość odcinka Bolków - Kamienna Góra"
  3. Konsorcjum PORR / GDDKiA (strona projektu)
    InvestorDescription
  4. Wroclaw.pl 31 Jul 2024
    StatusDelivery
  5. GDDKiA (gov.pl)
    Original dateDeliveryCostOutcome
    Schedule „Zakończenie robót wynikające z umowy: maj 2024 r.; Data udostępnienia do ruchu: 31 lipca 2024 r."
    Budget „Wartość kontraktu: 1 536 856 988,60 zł; całkowita wartość inwestycji ponad 1 785 mln zł"
    Scope „Zaprojektowanie i wybudowanie drogi S3 (...) zadanie III (...) o długości ok. 16,1 km"
    Original date „Zakończenie robót wynikające z umowy: maj 2024 r."
  6. Interia Motoryzacja 18 Sep 2025
    Outcome
    Utilisation „w ciągu pierwszego roku od oddania tego odcinka do ruchu zarejestrowano przejazd ponad 2,3 mln pojazdów"
  7. Inżynieria.com 9 Apr 2024
    Current date
    Current date „kontraktowy termin oddania drogi S3 został wyznaczony na 12 lipca, przy czym nie jest tożsamy z otwarciem odcinka"