A 20 km middle section of the S19 between Lublin and Kraśnik, from the Niedrzwica Duża interchange to the Kraśnik Północ interchange, on the Via Carpatia route. GDDKiA signed a design-and-build contract worth about PLN 498 million with Mota-Engil Central Europe in February 2018. The section opened to traffic on 21 May 2022 as the last missing piece of the Lublin – Rzeszów route. It includes 17 engineering structures, among them 12 viaducts and two crossings for large animals.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section
Timeline
- Delivery21 May 2022
Change history
- 21 May 2022stage: operational
Significance
The section completed the S19 expressway between Lublin and Rzeszów. According to reports from the opening, the trip between the cities shortened to about 90 minutes and through traffic left Niedrzwica Duża and Kraśnik. The PLN 498 million figure covers the contract for this part only; the three contracts on the Lublin – Kraśnik stretch total nearly PLN 1.13 billion.
Sources 6 · 5 independent
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Money.pl28 Feb 2018Investor
Investorzawarły z Generalną Dyrekcją Dróg Krajowych i Autostrad (GDDKiA) umowy na zaprojektowanie i budowę
- Inżynier Budownictwa1 Mar 2018Cost
CostŚrodkowy odcinek, od węzła Niedrzwica Duża do węzła Kraśnik Północ, zaprojektuje i wykona firma Mota-Engil Central Europe (ok. 20 km, 498 mln zł).
- Inżynier Budownictwa24 May 2022
- Interia Motoryzacja23 May 2022StatusStageDelivery
Status · Stage · DeliveryOdcinek o długości 20 km, został oddany do ruchu 21 maja 2022 r.
- [5]Bezpieczeństwo zdecydowanie się poprawi. Nowy odcinek S19 w Lubelskiem zostanie oddany do użytku ↗Polskie Radio Lublin20 May 2022
- Mota-Engil Central Europe