Design and construction of a 5.2 km section of the S19 expressway between Jawornik and Lutcza, the last S19 section in Podkarpackie sent to implementation. The design-and-build contract was signed on 13 November 2024 with the Gülermak (leader) and Budimex consortium. The contractor offered PLN 1,909,653,720 and a 59-month period. The key structure is a twin-tube tunnel of almost 3 km under Kamieniec hill, preceded by a viaduct of about 780 m. In April 2026 the voivode opened proceedings for the ZRID road permit, and the consortium continued design work. Completion is planned for 2031.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 4 carry no assessment yet. The timeline and sources below show what is known about the project. How to read this section
Timeline
- Original date2031
- Current date2031
Significance
Once the section is complete, planned for 2031, drivers will be able to use the S19 expressway from Rzeszów to the border at Barwinek. The media describe the tunnel as the longest road tunnel in Poland. About 3.8 km of the 5.2 km route is to run in the tunnel or on the viaduct.
Sources 6 · 5 independent
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Nowiny2413 Nov 2024Investor
InvestorPodpisaliśmy umowę na zaprojektowanie i budowę drogi ekspresowej S19 między Jawornikiem a Lutczą o długości 5,2 km.
- Rynek Infrastruktury21 Jul 2024Cost
CostWykonawca zaoferował zrealizowanie zadania za kwotę 1 909 653 720,00 zł w terminie 59 miesięcy, przedłużając okres gwarancji o 5 lat.
- Inżynieria.com23 Apr 2026Status
StatusObecnie trwają prace projektowe.
- Rzeszów News29 Apr 2026Stage
Stage22 kwietnia 2026 r. Wojewoda Podkarpacka wszczęła postępowanie administracyjne w sprawie wydania decyzji o zezwoleniu na realizację inwestycji drogowej (ZRID) dla odcinka między Jawornikiem a Lutczą.
- Interia Motoryzacja6 May 2026Current date
Current dateBrak opóźnień. Termin zakończenia: 2031 r.
- Interia Motoryzacja13 Nov 2024Original date
Original dateW efekcie plan zakłada, odcinek S19 Jawornik - Lutcza będzie gotowy w 2031.