A 12.5 km section of the S19 expressway between the Domaradz and Krosno (Iskrzynia) interchanges, procured as design-and-build. The contract with Mostostal Warszawa was signed on 7 November 2022 on the basis of a bid of PLN 1,063,251,940.57, and works were due to finish at the end of 2026. Physical progress was 13 per cent in May 2026. In April 2026 Mostostal withdrew from the contract for reasons it attributes to the contracting authority. GDDKiA treated that withdrawal as ineffective and in May 2026 terminated the contract itself, citing the contractor's fault. A tender to complete the section was announced in early September 2026, with bids due on 12 October.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 4 carry no assessment yet. The timeline and sources below show what is known about the project. How to read this section
Timeline
- Original dateDec 2026
Significance
The section links the Domaradz interchange with the Krosno area on the S19 between Rzeszów and Barwinek. The new contractor is to have 29 months for design and construction, and the project already holds a ZRID permit. The scope includes demolition and assessment of unaccepted works by the previous contractor. Mostostal says that changes after the environmental decision required lengthening structures by more than 700 m, with the extra works estimated at about PLN 550 million. GDDKiA does not accept those changes.
Sources 6 · 5 independent
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- conadrogach.pl27 Jul 2022Cost
CostNajkorzystniejszą złożyła spółka Mostostal Warszawa, która zaoferowała zrealizowanie tego odcinka Via Carpatia za kwotę 1 063 251 940,57 zł.
- Parkiet (komunikat ESPI)2 Apr 2026
- Forsal.pl14 May 2026StatusInvestor
Status · InvestorGDDKiA zerwała umowę z Mostostalem Warszawa na budowę odcinka S19 Domaradz – Krosno (Iskrzynia)
- Auto Świat2 Sep 2026Stage
StageGDDKiA ogłosiła przetarg na dokończenie budowy drogi ekspresowej S19 na odcinku pomiędzy węzłami Domaradz i Krosno.
- Interia Motoryzacja6 May 2026
- conadrogach.pl14 Mar 2024Original date
Original datewszystkie prace na odc. S19 Krosno – Domaradz powinny zostać ukończone z końcem 2026 roku