🚆Transportstrategic

S14 Łódź Western Bypass (Lublinek – Słowik)

completedstage: operationaldelivered
PLN 1.3 billion
contract value · data from 22 Aug 2019net or gross: not recorded≈ PLN 1.3 billion (value-by-stage, est., nominal)Sum of two design-and-build contract values from the GDDKiA contract pages: section I PLN 601.1 million and section II PLN 724.1 million. It is neither a final cost nor a total project value.Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The western bypass of Łódź on the S14 expressway is 28.5 km long and runs from the Łódź Lublinek interchange through Łódź Teofilów to Słowik. It was built under design-and-build terms in two GDDKiA contracts. Section I (12.2 km) was built by the Budimex and Strabag consortium, and section II (16.3 km) by STECOL. GDDKiA gives the contract values as PLN 601.1 million and PLN 724.1 million. The first section opened on 25 June 2022 and the second on 7 July 2023. The record covers the whole road, listed under the names Emilia – Lublinek – Słowik and Lublinek – Teofilów – Słowik.

How it went

Assessment: settled, as of 7 Jul 2023. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[1]
Utilisationin use[2]

Timeline

  1. Construction startOct 2018
  2. Delivery7 Jul 2023

Significance

The road links the A2 motorway with the S8 expressway and is meant to relieve Łódź, Pabianice, Zgierz, Konstantynów Łódzki and Aleksandrów Łódzki of through traffic. Section I has four interchanges and 17 engineering structures. The section I contractor reported that the value of the work, including the additional Teofilów interchange, was PLN 512 million net.

Sources 5 · 4 independent

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. GDDKiA, Mapa Stanu Budowy Dróg
    StatusCostDelivery
    Status · DeliveryW użytkowaniu Otwarcie drogi na zasadach stałej organizacji ruchu 7 lipca 2023 r.
    CostWartość umowy na projekt i budowę 724,1 mln zł
    DeliveryOtwarcie drogi na zasadach stałej organizacji ruchu 7 lipca 2023 r.
  2. GDDKiA, Mapa Stanu Budowy Dróg
    StageCostConstruction startUtilisation
    Stage · UtilisationW użytkowaniu Otwarcie drogi na zasadach stałej organizacji ruchu 25 czerwca 2022 r.
    CostWartość umowy na projekt i budowę 601,1 mln zł
    Construction startData podpisania umowy z wykonawcą 5 października 2018 r.
  3. Forsal.pl22 Aug 2019
  4. Money.pl5 Oct 2018
  5. Budimex15 Jun 2022
    Investor
    InvestorInwestorem jest Generalna Dyrekcja Dróg Krajowych i Autostrad w Łodzi.