Expansion of Fertiliser Production Capacity at Anwil (Włocławek)

completedstage: operationaldelayedover budget
PLN 1.7 billion
programme budget (multi-year) · data from 2023net or gross: not recorded≈ PLN 1.7 billion (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Expansion of nitrogen fertiliser production capacity at the ANWIL plants in Włocławek (ORLEN Group), worth approx. PLN 1.7 billion. As part of the investment, a third fertiliser line was built, consisting of a nitric acid production unit together with neutralisation, a granulation unit, and accompanying technical infrastructure. Thanks to it, the company's annual production capacity increased by approx. 50 percent – from 966 thousand tonnes to 1,461 thousand tonnes of fertiliser – and the product range was broadened by four products: coarse ammonium nitrate, ammonium sulphate nitrate, calcium ammonium nitrate with sulphur, and calcium ammonium nitrate with magnesium. The general contractor for the granulation unit was the Italian company Tecnimont. Completion was originally assumed for 2021, but the deadline was repeatedly postponed as a result of the pandemic, the war in Ukraine, and supply chain disruptions; construction was finalised in 2023, and the new products reached the market in the spring season of 2024.

How it went

Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one has an assessment with no confirmed quote. How to read this section

Scheduledelayed[2]
Budgetover budget[5]
Utilisationin use[6]
annual fertilizer sales
Current
1,032 mln ton (2024, wzrost o 154 tys. ton r/r); rozruch technologiczny instalacji granulacji kontynuowany w 2024 r.
Capacity or target
ok. 1,461 mln ton/rok (nowa moc po rozbudowie; poprzednia ok. 966 tys. ton)
Unit
tonnes/yr

Timeline

Slip: about 2 years vs. the original date (given as a year)

  1. AnnouncedDec 2018
  2. Original date2021
  3. Last stated dateJul 2023
  4. Delivery2023

Change history

  • Jul 2023stage: commissioning
  • 2023stage: operational
  • Dec 2018stage: announced

Significance

The largest investment in the history of the Włocławek company ANWIL, strengthening its position as a key domestic producer of nitrogen fertilisers. Increasing annual production capacity by approx. 50 percent (to 1,461 thousand tonnes) and broadening the portfolio by four new types of fertiliser strengthened the country's security in supplying agriculture with fertilisers. The investment provided approx. 200 additional jobs in a region for which ANWIL is the largest employer.

Sources 7 · 5 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Chemia i Biznes14 Dec 2018
    Original date
    Original dateInwestycja ma zostać ukończona jeszcze w 2021 r.
    LocationWartość strategicznej dla rozwoju włocławskiej spółki inwestycji szacowana jest na ok. 1,3 mld zł.
  2. Bankier.plOct 2022
    Last stated dateScheduleAnnouncedStage history
    Last stated date · ScheduleAnwil podpisał porozumienie z włoską firmą Tecnimont, które zakłada zmianę daty zakończenia budowy instalacji granulacji na koniec czerwca 2023 r. i oddanie jej do użytku na koniec lipca 2023 r.
    Announced · Stage historyW grudniu 2018 roku Orlen informował, że zgodził się na rozbudowę zdolności produkcyjnych nawozów w Anwilu
  3. ANWIL (Grupa ORLEN)Oct 2022
    InvestorStage history
    InvestorANWIL z Grupy ORLEN kontynuuje budowę kluczowej instalacji do produkcji nawozów azotowych, dzięki której zwiększy moce wytwórcze spółki o około 50 proc. i poszerzy ofertę produktową dla polskiego rolnictwa.
    Stage historyoddanie jej do użytku na koniec lipca 2023 r.
  4. Polskie Radio PiK27 Sep 2023
    StageStage history
    Stage · Stage historyTrzecia linia produkcyjna rozbudowana
  5. Polskie Radio 2427 Sep 2023
    StatusCostDeliveryBudget
    Status · DeliveryW ramach inwestycji powstały instalacje produkcyjne, jak również infrastruktura pomocnicza w tym magazyny mogące przechować do 25 tysięcy ton produktów.
    Cost · BudgetDodał, że wartość inwestycji wyniosła łącznie 1,7 miliardów złotych.
    BudgetJak podawano wtedy, zakładany całkowity koszt budowy trzeciej linii do produkcji nawozów to ok. 1,3 mld zł
  6. Chemia i Biznes17 Jun 2025
    Utilisation
    UtilisationŁączna sprzedaż nawozów osiągnęła w tym czasie poziom 1,032 mln ton