Expansion of Wrocław Airport (Operational Area, Stage I)

under construction stage: construction
377 mln PLN
contract value · 2026 prices ≈ 377 mln PLN (value-by-stage, est., nominal) funding: EU CEF2 (PLN 175 million)

The largest investment in the history of Wrocław Airport, comprising in its first stage the expansion of the operational area (airside): a new apron for 14 code C aircraft, a rapid exit taxiway, a new taxiway 2.5 km long, and a de-icing pad. The main contractor is STRABAG Infrastruktura Południe; work was inaugurated at the end of October 2024, with completion planned for December 2026. To connect the new infrastructure with the runway, the airport was closed in its entirety from 26 October to 4 December 2025. The investment, worth just under PLN 377 million net, is co-financed by the EU CEF2 instrument with an amount of PLN 175 million.

How it went

Assessment: too early to assess. Signals only where documented.

Delivery partial
Schedule on time

Timeline

  1. Construction start Oct 2024
  2. Original date Dec 2026
  3. Current date Dec 2026

Change history

  • Oct 2024 stage: construction

Significance

The expansion nearly doubles the airport's operational capabilities: the new apron will allow 28 aircraft to be parked simultaneously, and the airport's target capacity is to increase to 8-10 million passengers per year (from a level of approx. 4-4.5 million). The full closure of the airport for 40 days (26.10-4.12.2025) was a rare precedent on a national scale, necessary to integrate the new infrastructure with the runway.

Sources 5 · 4 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. Wroclaw.pl 2025
    CostSignificanceDescription
  2. Money.pl 2025
    CostSignificance
  3. STRABAG 2024
    InvestorStageDescription
    Investor „STRABAG rozbuduje Port Lotniczy Wrocław"
  4. Rynek Lotniczy 26 Apr 2026
    StatusStageCostConstruction startCurrent dateOriginal date
    Status „Zainaugurowana pod koniec października 2024 r. inwestycja jest największą w historii wrocławskiego lotniska, a jej koniec zaplanowany jest na grudzień 2026 r."
    Stage „W ramach inwestycji w ciągu 26 miesięcy prac budowlanych powstaje nowa płyta postojowa na 14 samolotów kodu C, droga szybkiego zjazdu, nowa mierząca 2,5 km droga kołowania i płyta do odladzania."
    Cost „Całkowity koszt inwestycji, która niemal podwoi możliwości operacyjne lotniska w stolicy Dolnego Śląska to niespełna 377 mln złotych netto (463,5 mln zł brutto)."
    Construction start „Zainaugurowana pod koniec października 2024 r. inwestycja jest największą w historii wrocławskiego lotniska"
    Current date „jej koniec zaplanowany jest na grudzień 2026 r."
    Original date „Zgodnie z harmonogramem zakończenie pierwszego etapu rozbudowy planowane jest na grudzień 2026 roku."
    locations „Całkowity koszt inwestycji, która niemal podwoi możliwości operacyjne lotniska w stolicy Dolnego Śląska to niespełna 377 mln złotych netto"
  5. Wroclaw.pl 2025
    StatusSignificance