Expansion of the Żelazny Most Mining Waste Disposal Facility – Southern Quarter
Construction of a new Southern Quarter as part of the Żelazny Most Mining Waste Disposal Facility (OUOW) – the largest tailings storage facility in Europe, owned by KGHM Polska Miedź. The expansion included preparatory works and the construction of dams surrounding the new quarter and was intended to ensure continuity of depositing waste from KGHM's mining and metallurgical chain for years to come. The investment was carried out by Budimex, and the facility was officially opened at the turn of 2021, seven months ahead of schedule despite the pandemic.
How it went
Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section
- Current
- ~30 mln ton rocznie
- Capacity or target
- Kwatera Południowa: pojemność docelowa ~170 mln m³, eksploatacja planowana 2021–2042
- Unit
- mn tonnes/yr
Timeline
Ahead: under a year
- Delivery3 Nov 2021
Change history
- 3 Nov 2021stage: operational
Significance
The expansion secures the continuity of depositing approx. 30 million tonnes of tailings per year, which is crucial for the uninterrupted operation of KGHM's entire mining and metallurgical chain. Together with the newly added Southern Quarter, the facility covers more than 2,000 ha, remaining the largest storage facility of its kind in Europe. A new method of building dams on the outside of the quarter was applied, intended to improve safety and environmental protection in the region of the Legnica-Głogów Copper District.
Sources 7 · 4 independent · 7 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Ministerstwo Aktywów Państwowych (gov.pl)3 Nov 2021StatusStageCostStage historyDelivery
StatusSiedem miesięcy przed terminem ukończono rozbudowę
StageKwatera Południowa Żelaznego Mostu KGHM oficjalnie otwarta
CostWartość nowej inwestycji to ponad 1 mld zł.
Stage history03.11.2021
DeliverySiedem miesięcy przed terminem ukończono rozbudowę Obiektu Unieszkodliwiania Odpadów Wydobywczych Żelazny Most.
- [2]KGHM otwiera Kwaterę Południową. Innowacyjne rozwiązania w trosce o bezpieczeństwo i środowisko ↗archived ✓KGHM Polska Miedź S.A. (biuro prasowe)3 Nov 2021DeliveryInvestor
NameKwatera Południowa stanowiąca element Obiektu Unieszkodliwiania Odpadów Wydobywczych Żelazny Most to największa inwestycja KGHM Polska Miedź S.A. od 2018 roku
TypeRozbudowa Obiektu, mimo pandemii została ukończona 7 miesięcy przed terminem
Deliveryśroda, 03 listopada, 2021
Investorto największa inwestycja KGHM Polska Miedź S.A. od 2018 roku
LocationZlokalizowany na Dolnym Śląsku OUOW Żelazny Most
- Inżynieria.com8 May 2018
- Wikipedia (pl)
- [5]KGHM nie zwalnia tempa – dobiega końca pierwsza faza budowy Kwatery Południowej OUOW Żelazny Most ↗archived ✓KGHM Polska Miedź S.A. (biuro prasowe)2020Utilisation
UtilisationDocelowa objętość Kwatery Południowej ma wynosić około 170 mln m³
- Inżynieria.com3 Nov 2021ScheduleUtilisation
ScheduleNajwiększa inwestycja miedziowego giganta od 2018 r. została ukończona siedem miesięcy przed terminem
UtilisationRocznie zostaje tu odprowadzonych około 30 mln ton odpadów