Gdynia Shipyard restructuring and aid (2004–2008)

cancelledabandoned
EUR 497 million
programme budget (multi-year) · data from 16 Jul 2008net or gross: not recorded≈ PLN 2.1 billion (value-by-stage, est., nominal)Nominal value of state aid granted since 2004, not a construction cost. Production guarantees of EUR 915 million are not included. The amount is given in EUR by the European Commission.Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A programme to rescue the Gdynia Shipyard with public funds from 2004, mainly recapitalisation and loans. According to the European Commission the yard received aid worth EUR 497 million and production guarantees of EUR 915 million (nominal value). In July 2008 the Commission found the restructuring plans incompatible with state aid rules, and in November 2008 it found the aid illegal. In 2010 assets due to be put up for sale included a large dock valued at about PLN 100 million.

Why it failed

In November 2008 the European Commission found the public aid to the yard illegal. The company came under the special shipyard act on liquidation and sale of assets, in force from the start of 2009.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 4 carry no assessment yet. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Construction start2004

Change history

  • Nov 2008status: cancelledThe European Commission found the aid illegal and the company went into liquidation.

Significance

In November 2008 the European Commission found the aid illegal. A special shipyard act, in force from the start of 2009, governs the liquidation of the company and the sale of its assets. A tender procedure for the unsold part of the assets was due to start by the end of May 2010.

Sources 4 · 4 independent

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. e-prawnik.pl16 Jul 2008
    CostConstruction startDescription
    CostStocznia Gdynia korzystała z różnych środków pomocy (przede wszystkim środków na dokapitalizowanie oraz pożyczek) o wartości 497 mln EUR
    Construction startRozpatrywane środki pomocy państwa zostały przyznane w 2004 r. po wejściu Polski do Unii Europejskiej.
    Descriptiona także z gwarancji na produkcję w wysokości 915 mln EUR (wartość nominalna pomocy)
    DescriptionKomisja Europejska stwierdziła, że obecne plany restrukturyzacji Stoczni Gdynia i Stoczni Szczecińskiej przedstawione przez władze polskie są niezgodne z wytycznymi wspólnotowymi dotyczącymi pomocy państwa w celu ratowania i restrukturyzacji zagrożonych przedsiębiorstw
  2. Rzeczpospolita24 May 2010
    StatusFailure descriptionDescriptionSignificance
    StatusZasady likwidacji obu spółek i sprzedaży ich majątku określa obowiązująca od początku 2009 r. specustawa stoczniowa przygotowana przez rząd.
    Failure descriptionSprzedaż majątku zakładów i zwolnienia pracowników to efekt uznania przez Komisję Europejską w listopadzie 2008 r. pomocy publicznej udzielonej w przeszłości stoczniom w Szczecinie i Gdyni za nielegalną.
    DescriptionInwestorzy będą mogli kupić m.in. duży dok o wartości ok. 100 mln zł
    SignificanceDo końca maja ruszy procedura przetargowa dla niesprzedanych w ubiegłym roku części majątku stoczni Gdynia.
  3. Gazeta Prawna29 May 2008
    Investor
    InvestorSkarb Państwa zdecydował o uruchomieniu programu dokapitalizowania Stoczni Gdynia kwotą 515 mln zł i konwersji 160 mln długu Stoczni Nowa na akcje
  4. Mondaq (CMS Cameron McKenna)21 Jul 2008