Regional Broadband Networks (RSS) – Regional Operational Programmes 2007–2013

completedstage: operationaldelivered
PLN 3.0 billion
programme budget (multi-year) · data from 2016net or gross: not recorded≈ PLN 3.0 billion (value-by-stage, est., nominal)funding: EU funds, local governmentLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

An umbrella record covering the construction of the regional broadband networks (RSS), fibre-optic backbone-and-distribution networks implemented by beneficiaries under the regional operational programmes of the 2007–2013 perspective (and, financed separately, the Eastern Poland Development Operational Programme for the Lublin, Podlaskie, Podkarpackie, Świętokrzyskie and Warmian-Masurian voivodeships). The aim of the programme was to eliminate so-called digital-exclusion white spots and bring backbone infrastructure closer to residents of areas where it was not commercially viable for operators to invest. According to a summary by the Ministry of Digital Affairs (June 2016), over 23,000 km of new network was built during the 2007–2013 perspective, and nearly 6,000 km of network was delivered using existing infrastructure (approximately 30,000 km in total); 2,927 nodes were created (286 backbone and 2,641 distribution nodes), and beneficiaries spent a total of over PLN 3 billion implementing the projects. The record is listed as an umbrella to avoid double-counting with individual regional projects. Such projects include Internet dla Mazowsza, the Greater Poland Broadband Network (Wielkopolska Sieć Szerokopasmowa) and the Eastern Poland Broadband Network (Sieć Szerokopasmowa Polski Wschodniej). A representative example of a regional project is the Lower Silesian Broadband Network (Dolnośląska Sieć Szerokopasmowa / Dolnośląska Sieć Szkieletowa), approximately 1,616 km of fibre-optic lines, co-financed from the European Regional Development Fund under the Regional Operational Programme for the Lower Silesian Voivodeship for 2007–2013 (EU co-financing of approximately PLN 149.7 million), with a total value of around PLN 200 million, completed in 2015.

How it went

Assessment: settled, as of 3 Jun 2016. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 3 carry no assessment yet. How to read this section

No source calls this a delay and the card makes no assessment here, but the dates recorded on this project differ by 2 years: originally 2013, currently 2015.

Deliverydelivered[1]

Timeline

  1. Announced2007
  2. Original date2013
  3. Delivery2015

Significance

The regional broadband networks of the 2007–2013 perspective were the state's main instrument for tackling digital-exclusion white spots before the era of the Digital Poland Operational Programme. Nationwide, around 30,000 km of backbone-and-distribution network and 2,927 nodes were built, bringing fibre-optic infrastructure to commercially unviable areas and creating a wholesale layer used by last-mile operators. The programme was at the same time the subject of criticism and implementation problems (delays, disputes with infrastructure operators, incomplete utilisation of part of the network).

Sources 4 · 3 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Cyfryzacji (gov.pl)3 Jun 2016
    StatusStageCostAnnouncedOriginal dateInvestorFundingDelivery
    Status · DeliveryW ramach perspektywy 2007-2013 w Polsce powstało prawie 30 tys. km sieci szkieletowo-dystrybucyjnych: wybudowano ponad 23 tys. km sieci, a prawie 6 tys. km sieci zrealizowano z wykorzystaniem istniejącej infrastruktury.
    StageW ramach budowy sieci szerokopasmowych powstało 2 927 węzłów (w tym 286 szkieletowych i 2 641 dystrybucyjnych)
    CostNa realizację projektów Beneficjenci wydatkowali łącznie ponad 3 miliardy złotych
    Announced · Original dateEfekty realizacji Regionalnych Sieci Szerokopasmowych w perspektywie 2007-2013
    Investor · FundingProjekty były współfinansowane z regionalnych programów operacyjnych oraz Programu Operacyjnego Rozwój Polski Wschodniej (województwa: lubelskie, podlaskie, podkarpackie, świętokrzyskie i warmińsko-mazurskie)
  2. Rzeczpospolita (rp.pl)
  3. Wikipedia (pl)
  4. Urząd Marszałkowski Województwa Dolnośląskiego27 Apr 2015
    DeliveryFunding
    DeliveryW poniedziałek, 27 kwietnia oficjalnie zakończono inwestycję „Likwidacja obszarów wykluczenia informacyjnego i budowa dolnośląskiej sieci szkieletowej”.

    year taken from the source's publication date (27 Apr 2015)

    FundingRównież 23 gminy udzieliły wsparcia finansowego w łącznej wysokości 5,5 mln zł.