Line 8: Sędziszów – Sitkówka Nowiny (two contracts)

in preparationstage: tender
PLN 1.5 billion
contract value · data from 14 Sep 2026incl. VAT≈ PLN 1.5 billion (value-by-stage, est., nominal)funding: multilateral development bankLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Modernisation of two sections of railway line 8 in Świętokrzyskie voivodeship, Sędziszów – Jędrzejów – Miąsowa and Miąsowa – Sitkówka Nowiny, over 50 km in total. On 14 September 2026 PKP Polskie Linie Kolejowe signed two contracts worth more than PLN 1.45 billion gross. ZUE will carry out the first, worth PLN 960 million. The second, worth PLN 496 million, goes to Pomorskie Przedsiębiorstwo Mechaniczno-Torowe with Transkol. The contractors will replace about 134 km of track together with the overhead line and build 43 engineering structures. Completion is planned for the second half of 2029. The works belong to the Skarżysko-Kamienna – Kielce – Kozłów project, supported by an EIB loan of up to EUR 450 million.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 4 carry no assessment yet. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Current dateDec 2029

Change history

  • Sep 2026stage: tender

Significance

After the upgrade, passenger trains will run at up to 140 km/h and freight trains at up to 120 km/h. The Radkowice stop will be converted into a station, which improves capacity where the line meets line 73 to Busko-Zdrój. Station tracks will handle freight trains 750 m long. The middle section through Kielce has not yet entered the construction stage.

Sources 4 · 4 independent

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. wKielcach.info (PAP)14 Sep 2026
    StatusStageCostInvestorFunding
    Status · Stage · InvestorPKP Polskie Linie Kolejowe podpisały umowy na przebudowę dwóch kluczowych odcinków linii kolejowej nr 8 w województwie świętokrzyskim
    CostŁączna wartość obu kontraktów przekracza 1,45 mld zł brutto.
    FundingFinansowanie inwestycji wspiera Europejski Bank Inwestycyjny kredytem w wysokości do 450 mln euro.
  2. Inżynieria.com15 Sep 2026
    Current date
    Current dateZakończenie robót zaplanowano na drugą połowę 2029 r.
  3. Raport Kolejowy20 Sep 2026
  4. Muratorplus29 Sep 2026