Reconstruction of Warszawa Wschodnia station
The modernization of Warszawa Wschodnia station and the Warszawa Stadion stop, carried out by the infrastructure manager PKP Polskie Linie Kolejowe S.A. The contractor is Torpol; a contract worth nearly PLN 3.64 billion gross was signed on 12 June 2026. Scope: the reconstruction of seven roofed platforms of uniform height, 14 elevators, escalators, the modernization of underground passages, a new viaduct, and the replacement of tracks, switches, and the traction network. Construction works are to start in December 2026 and continue until the end of 2029. The investment is co-financed from the EU FEnIKS program.
How it went
Assessment: too early to assess. Signals only where documented.
Timeline
- Original date 2029
- Current date 2029
Change history
- 12 Jun 2026 stage: tender
Significance
The modernization covers one of the busiest stations in the Warsaw railway junction, through which nearly a thousand trains pass per day. The uniform, roofed platforms, together with 14 elevators and escalators, are intended to improve accessibility and passenger comfort, while the replacement of tracks, switches, and the traction network, together with a new viaduct, is to increase capacity and traffic reliability. The undertaking continues the reconstruction of the capital's railway junction begun with the modernization of Warszawa Zachodnia station.
Sources 5
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- NowaWarszawa.pl 28 Jan 2026Status
- Architektura-murator / Muratorplus.pl 12 Jun 2026CostSignificanceDescription
- PKP Polskie Linie Kolejowe S.A. 12 Jun 2026InvestorCurrent dateOriginal datecost.fundingSignificance
Investor „Podpisaliśmy umowę na modernizację stacji Warszawa Wschodnia i przystanku Warszawa Stadion z firmą Torpol o wartości blisko 3 miliardów złotych."
cost.funding „Inwestycja będzie współfinansowana ze środków programu unijnego Fundusze Europejskie na Infrastrukturę, Klimat i Środowisko (FEnIKS)."
Current date „Prace mają rozpocząć się w grudniu tego roku i potrwać do końca 2029 r."
- Sektorkolejowy.pl 12 Jun 2026CostStageStatus
Status „Polskie Linie Kolejowe i Torpol podpisali dziś kontrakt na modernizację Warszawy Wschodniej"
Cost „Wartość umowy wynosi blisko 3,64 mld zł brutto"
- Forsal.pl 12 Jun 2026Current dateSignificance
Original date „wszystkie prace potrwają do 2029 roku"