Reconstruction of the runway and taxiways at Rzeszów-Jasionka Airport (CEF Military Mobility)
The reconstruction of the operational infrastructure of Rzeszów-Jasionka Airport named after the Ulma Family includes the second stage of the construction of a parallel taxiway (approximately 1,087 m) together with two perpendicular connectors to the runway, the expansion of the aircraft turnaround pad, and the reconstruction of a 700-meter section of the runway. The contractor selected in the tender is Strabag, and the value of the contract is approximately PLN 113.8 million. The investment is co-financed from European Union funds under the Connecting Europe Facility (CEF Military Mobility) 2021-2027 in the amount of approximately PLN 48 million (EUR 11 million); the remaining funds come from the airport operator and its shareholders — the Podkarpackie Voivodeship Self-Government (PLN 20 million) and Polish Airports (Polskie Porty Lotnicze) (PLN 15 million). The works are carried out while maintaining the continuity of flight operations.
How it went
Assessment: too early to assess. Signals only where documented.
Timeline
- Construction start Apr 2025
- Original date Sep 2026
- Current date Sep 2026
Change history
- Apr 2025 stage: construction
Significance
The modernization of the runway and taxiways is intended to increase the capacity and operational capabilities of the Jasionka airport, which serves as a key NATO logistics hub and the main transshipment point for aid to Ukraine. Qualifying the investment for financing under Military Mobility underscores its dual, civil-military character. The reconstruction of the 700-meter section of the runway was completed in October 2025, restoring the full length of the runway (3,200 m) three weeks ahead of the original schedule; construction of the parallel taxiway is to be completed in 2026.
Sources 6 · 6 archived
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- Port Lotniczy Rzeszów-Jasionka 18 Mar 2025CostStatusStageConstruction startOriginal dateInvestor
Stage „Inwestycja będzie realizowana od kwietnia 2025 do połowy września 2026 roku"
cost.funding „Dofinansowanie unijne na to zadanie wynosi ok. 48 mln zł"
Investor „Port Lotniczy Rzeszów-Jasionka im. Rodziny Ulmów"
- Port Lotniczy Rzeszów-Jasionka 23 Oct 2025StatusStageCurrent dateSignificance
Status „Równocześnie z zakończonymi działaniami trwają prace dotyczące II etapu budowy równoległej drogi kołowania. Zgodnie z harmonogramem, zakończenie budowy około 1.100 metrów drogi kołowania planowane jest w trzecim kwartale 2026 roku."
Current date „Zgodnie z harmonogramem, zakończenie budowy około 1.100 metrów drogi kołowania planowane jest w trzecim kwartale 2026 roku."
- dlapilota.pl 27 Mar 2025CostInvestor
- czytajrzeszow.pl 27 Mar 2025CostInvestor
Cost „Latem zeszłego roku ogłoszono przetarg na prace budowlane, a 31 grudnia okazało się, że wygrała go firma Strabag z Pruszkowa, która wyceniła to zadanie na 113,8 mln zł."
- Klub Jagielloński 3 Dec 2022Significance
- WNP.pl 23 Oct 2025Current date