🚆Transportstrategic

Reconstruction of the runway and taxiways at Rzeszów-Jasionka Airport (CEF Military Mobility)

under constructionstage: commissioning
114 mln PLN
contract value · data from Mar 2025net or gross: not recorded≈ 114 mln PLN (value-by-stage, est., nominal)funding: EU co-funding under the "Connecting Europe Facility" 2021-2027 (CEF Military Mobility) – approx. PLN 48 million (EUR 11 million), Contribution from Rzeszów-Jasionka Airport – approx. PLN 30.8 million, Subcarpathian Voivodeship self-government – PLN 20 million, Polish Airports (PPL) – PLN 15 million

The reconstruction of the operational infrastructure of Rzeszów-Jasionka Airport named after the Ulma Family includes the second stage of the construction of a parallel taxiway (approximately 1,087 m) together with two perpendicular connectors to the runway, the expansion of the aircraft turnaround pad, and the reconstruction of a 700-meter section of the runway. The contractor selected in the tender is Strabag, and the value of the contract is approximately PLN 113.8 million. The investment is co-financed from European Union funds under the Connecting Europe Facility (CEF Military Mobility) 2021-2027 in the amount of approximately PLN 48 million (EUR 11 million); the remaining funds come from the airport operator and its shareholders – the Podkarpackie Voivodeship Self-Government (PLN 20 million) and Polish Airports (Polskie Porty Lotnicze) (PLN 15 million). The works are carried out while maintaining the continuity of flight operations.

How it went

Assessment: too early to assess, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverypartial[2]

Timeline

  1. Original dateSep 2026
  2. Current dateDec 2026

Change history

  • Aug 2026stage: commissioning

Significance

The modernization of the runway and taxiways is intended to increase the capacity and operational capabilities of the Jasionka airport, which serves as a key NATO logistics hub and the main transshipment point for aid to Ukraine. Qualifying the investment for financing under Military Mobility underscores its dual, civil-military character. The reconstruction of the 700-meter section of the runway was completed in October 2025, restoring the full length of the runway (3,200 m) three weeks ahead of the original schedule; construction of the parallel taxiway is to be completed in 2026.

Sources 7 · 6 independent · 6 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Port Lotniczy Rzeszów-Jasionka18 Mar 2025
    FundingOriginal dateInvestor
    FundingDofinansowanie unijne na to zadanie wynosi ok. 48 mln zł
    Original dateInwestycja będzie realizowana od kwietnia 2025 do połowy września 2026 roku
    Investor · LocationPort Lotniczy Rzeszów-Jasionka im. Rodziny Ulmów
    FundingDofinansowanie unijne na to zadanie wynosi ok. 48 mln zł.
    FundingPort Lotniczy Rzeszów-Jasionka im. Rodziny Ulmów (ok. 30,8 mln zł)
  2. Port Lotniczy Rzeszów-Jasionka23 Oct 2025
    StatusCurrent dateDelivery
    StatusRównocześnie z zakończonymi działaniami trwają prace dotyczące II etapu budowy równoległej drogi kołowania. Zgodnie z harmonogramem, zakończenie budowy około 1.100 metrów drogi kołowania planowane jest w trzecim kwartale 2026 roku.
    Current dateZgodnie z harmonogramem, zakończenie budowy około 1.100 metrów drogi kołowania planowane jest w trzecim kwartale 2026 roku.Termin zakończenia budowy podany w październiku 2025 r.
    DeliveryPort Lotniczy Rzeszów-Jasionka im. Rodziny Ulmów zakończył przebudowę 700-metrowego odcinka drogi startowej i przywrócił do pełnej eksploatacji całą długość pasa startowego tj. 3200 metrów.
  3. dlapilota.pl27 Mar 2025
    Funding
    FundingPozostała kwota to wkład własny spółki zarządzającej lotniskiem oraz dotacja właścicieli lotniska – samorządu województwa (20 mln zł) i Polskich Portów Lotniczych (15 mln zł)
  4. czytajrzeszow.pl27 Mar 2025
    Cost
    CostLatem zeszłego roku ogłoszono przetarg na prace budowlane, a 31 grudnia okazało się, że wygrała go firma Strabag z Pruszkowa, która wyceniła to zadanie na 113,8 mln zł.
  5. Klub Jagielloński3 Dec 2022
  6. WNP.pl17 Dec 2025
  7. TransInfo4 Aug 2026
    StageStage historyCurrent date
    Stage · Stage historyObecnie prowadzone są testy zamontowanych systemów oraz przygotowania do odbiorów technicznych.
    Current dateNowy odcinek ma około 1 087 m długości, a jego operacyjne uruchomienie zaplanowano na IV kwartał 2026 r.Termin włączenia do użytkowania po certyfikacji ULC i publikacji w AIP (IV kwartał 2026 r.). Port poinformował 4 sierpnia 2026 r. o zakończeniu zasadniczych robót budowlanych, przed umownym terminem z połowy września.