← all projects
🏭Industrystrategic

HBO Project – Hydrocracking Oil Block at the Gdańsk Refinery

under constructionstage: construction
PLN 1.8 billion
programme budget (multi-year) · data from 2024net or gross: not recorded≈ PLN 1.8 billion (value-by-stage, est., nominal)funding: the investor’s own fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The HBO Project (Hydrocracking Oil Block) is a strategic investment by the ORLEN Group carried out at the refinery in Gdańsk (Pomorskie Voivodeship), which is part of the assets of the former LOTOS Group acquired after the merger. The new installation complex is intended to enable the production of up to 400 thousand tons per year of high-quality Group II base oils, used to make engine and lubricating oils in industry and automotive transport, and, in addition, fuel intermediates, gasoline, and diesel oil. Construction of the main installation and accompanying facilities began in August 2022; at the end of June 2024, the progress of the entire project stood at approximately 70 percent. According to the schedule, the technological start-up of the main installation was to begin no later than the fourth quarter of 2025, and the installations are to reach full operational capacity in the first half of 2026. The value of the investment is estimated at more than PLN 1.8 billion.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Construction startAug 2022
  2. Original date2026
  3. Current date2026

Change history

  • Aug 2022stage: construction

Significance

The installation is intended to be Poland's first source of Group II base oils, reducing the domestic market's dependence on imports of these high-quality products. The target capacity of up to 400 thousand tons per year will make it possible to supply producers of engine oils and lubricants for industry and the automotive sector, while the additional production of fuel intermediates, gasoline, and diesel oil strengthens the processing potential of the Gdańsk refinery. The investment constitutes one of the key elements of the modernization of the former LOTOS Group assets within the ORLEN Group.

Sources 5 · 4 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. PAP MediaRoomJul 2024
  2. PAP MediaRoom5 Jul 2024
    StatusStageProgressConstruction startCurrent dateCostInvestor
    Status · ProgressZaawansowanie Projektu HBO na koniec czerwca 2024 roku wynosi ok. 70 proc.
    Stage · Construction startBudowa instalacji podstawowej oraz obiektów towarzyszących Projektu HBO w Gdańsku rozpoczęła się w sierpniu 2022 roku.
    Current datew pierwszej połowie 2026 roku - instalacje i obiekty Projektu HBO osiągną całkowitą zdolność operacyjną
    CostWarta ponad 1,8 mld zł inwestycja, umożliwiająca wyprodukowanie nawet 400 tys. ton olejów bazowych grupy II rocznie
    Investorstrategiczna inwestycja Grupy ORLEN w Gdańsku
    Locationrafinerii w Gdańsku
  3. Trojmiasto.plJul 2024
    Original dateCost
    Original datedo połowy 2026 r. instalacja ma osiągnąć pełną zdolność operacyjną
    CostRealizowany nakładem ponad 1,8 mld zł
  4. PortalSamorzadowy.pl
  5. Funding
    FundingThe Company has granted a PLN 0.34bn loan to LOTOS Oil to finance the first phase of works under the HBO Project. Full external funding for the HBO Project is currently being arranged.