Program 10+ (expansion of the Grupa LOTOS refinery in Gdańsk)

completedstage: operationaldelivered
PLN 5.5 billion
programme budget (multi-year) · data from 2011net or gross: not recorded≈ PLN 5.5 billion (value-by-stage, est., nominal)funding: private finance, the investor’s own fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Program 10+ was the largest investment programme of Grupa LOTOS S.A. and one of the largest industrial undertakings in Poland after 1989. Grupa LOTOS began implementing the programme in 2007, and it was completed on 28 March 2011, when the completion of the undertaking was ceremonially marked at the Gdańsk refinery. Program 10+ as a whole comprised 50 different installations that were built or modernised; construction work took 43 months (3.5 years), and 3,500 people from more than 90 companies were involved in the project. The aim was to increase the crude oil processing capacity of the Gdańsk refinery to 10.5 million tonnes per year, representing a 75% increase in nominal processing capacity. Design, construction and equipment purchases were worth approximately PLN 5.5 billion (the total value of the expansion is also given as approximately EUR 1.43 billion). The owner and investor was Grupa LOTOS S.A., a company with a majority stake held by the State Treasury.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[1]
Utilisationin use[3]
zdolność przerobu ropy naftowej
Current
przerób pogłębiony do 10,5 mln ton rocznie (2011)
Capacity or target
10,5 mln ton/rok

Timeline

  1. Construction start2007
  2. Delivery28 Mar 2011

Change history

  • 28 Mar 2011stage: operational
  • 2007stage: construction

Significance

Program 10+ was one of the largest industrial undertakings in the Polish economy of the early 21st century and the largest investment programme of Grupa LOTOS. Thanks to 50 new or modernised installations, the processing capacity of the Gdańsk refinery increased by 75%, to 10.5 million tonnes of crude oil per year, which significantly increased processing capacity and deep conversion (fuel yield) in the national refining sector. The investment strengthened Gdańsk's position as one of the two main crude oil processing centres in Poland.

Sources 9 · 8 independent · 7 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Grupa LOTOS S.A.Mar 2011
    StatusStageCostDelivery
    Status · Delivery28 marca br. w gdańskiej rafinerii Grupy LOTOS nastąpiło uroczyste zakończenie realizacji Programu 10+

    year taken from the source's publication date (Mar 2011)

    Stageostatnia z 50, które były budowane lub modernizowane w ramach Programu 10+
    Costprojektowanie, budowa oraz zakupy sprzętu warte są około 5,5 mld złotych
    StatusOddana właśnie do uruchomienia instalacja odasfaltowania rozpuszczalnikowego (ROSE) to ostatnia z 50, które były budowane lub modernizowane w ramach Programu 10+.
  2. Trojmiasto.pl23 Mar 2011
  3. Gedanopedia
    Utilisation
    UtilisationDzięki zakończeniu inwestycji zrealizowanych w ramach Programu 10+ przerób ropy naftowej w 2011 wyniósł 9,2 mln ton – najwyższy poziom w historii funkcjonowania gdańskiej rafinerii.
  4. Fluor Corporation
    Construction start
    Construction startIn 2007, LOTOS began its largest investment project, '10+ Programme,' with the target to expand refinery capacity, increase efficiency and reduce the impact of the refinery on the environment.
  5. Wikipedia (en)
    Investor
    InvestorThe Polish state was the majority shareholder with 53% percent
  6. Funding
    FundingZarząd podpisał wtedy porozumienie w sprawie kredytowania Programu 10+ opiewające na łączną kwotę 1,75 mld dolarów.
  7. Funding
    FundingOkoło 70 proc. tej kwoty spółka chce pozyskać z kredytów, a pozostałe 30 proc. pochodzić będzie ze środków własnych.