Warsaw-Modlin Airport

completedstage: operationaldelivered
PLN 451 million
estimate · data from 2012net or gross: not recorded≈ PLN 451 million (value-by-stage, est., nominal)funding: EU funds, local government, other sourcesLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

An international airport in Nowy Dwór Mazowiecki, about 35 km northwest of central Warsaw, established on the basis of a former military airfield as a base for low-cost airlines. On 8 November 2006, the co-shareholders concluded an agreement establishing the company Mazowiecki Port Lotniczy Warszawa-Modlin Sp. z o.o., whose shareholders are the Agencja Mienia Wojskowego, Przedsiębiorstwo Państwowe Porty Lotnicze, the Mazowieckie Voivodeship, and the City of Nowy Dwór Mazowiecki. Construction officially began on 8 October 2010, and the airport opened on 7 July 2012. The construction of the airport cost PLN 451,400,000. The terminal's capacity was set at 3–3.5 million passengers per year.

How it went

Assessment: settled, as of 19 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[1]
Utilisationin use[1]

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

annual number of passengers vs terminal capacity
Current
3 400 967 (2023); 2 794 464 (2024) (2023-2024)
Capacity or target
3-3,5 mln rocznie
Unit
passengers

Timeline

  1. Announced8 Nov 2006
  2. Construction start8 Oct 2010
  3. Delivery7 Jul 2012

Change history

  • 7 Jul 2012stage: operational
  • 8 Oct 2010stage: construction

Significance

Warsaw-Modlin Airport became the second airport serving the Warsaw metropolitan area and the main national base for low-cost airlines (including Ryanair and Wizz Air), relieving Chopin Airport in the low-cost segment. Opened on 7 July 2012, with a capacity set at 3–3.5 million passengers per year, the airport quickly approached its capacity limit: in 2023 it handled 3,400,967 passengers, and in 2024 – 2,794,464 passengers. The high level of terminal utilization became the basis for plans to expand it to serve 7–8 million passengers per year.

Sources 5 · 3 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Wikipedia (pl)
    StatusStageInvestorCostAnnouncedConstruction startDeliveryUtilisation
    Status · Stage · DeliveryOtwarcie lotniska odbyło się 7 lipca 2012
    Investor · Announced8 listopada 2006 współudziałowcy budowy portu lotniczego zawarli porozumienie, tworząc spółkę Mazowiecki Port Lotniczy Warszawa-Modlin.
    CostBudowa portu lotniczego kosztowała 451 400 000 zł
    Construction startBudowę oficjalnie rozpoczęto 8 października 2010
    Utilisationprzepustowość określono na poziomie 3–3,5 mln osób rocznie
  2. Rzeczpospolita (rp.pl)15 Jul 2012
    Funding
    FundingJej udziałowcami są: Agencja Mienia Wojskowego, województwo mazowieckie, Przedsiębiorstwo Państwowe Porty Lotnicze oraz miasto Nowy Dwór Mazowiecki.
  3. Wikipedia (en)
  4. money.pl19 Dec 2024
  5. Funding
    FundingPrzedsięwzięcie zostało dofinansowane przez RPO WM w kwocie 76 mln złotych.
    FundingDo tej pory województwo objęło udziały w podwyższonym kapitale zakładowym spółki na kwotę blisko 100 mln złotych, a teraz zabezpieczyło na ten cel kolejne 200 mln złotych.
    FundingŚrodków na budowę lotniska w Modlinie udzieli Bank PKO SA. Proces ten będzie możliwy dzięki emisji obligacji.