Polimery Police (PDH and polypropylene installation)

under constructionstage: commissioningdelayed
7.2 bn PLN
programme budget (multi-year) · data from 22 Jun 2023net or gross: not recorded≈ 7.2 bn PLN (value-by-stage, est., nominal)

A petrochemical complex in Police built by the special-purpose company Grupa Azoty Polyolefins: a propane dehydrogenation (PDH) installation with a capacity of 429 thousand tonnes of propylene per year, a polypropylene installation with a capacity of 437 thousand tonnes per year, and its own maritime gas terminal for importing propane and ethylene by sea. The project budget exceeded PLN 7.2 billion against the original 2015 estimates of approximately PLN 1.7 billion. Polypropylene production was launched in June 2023, but the installations did not reach full, stable operation, and the indebted company entered restructuring proceedings in November 2025. On 31 March 2026, Orlen signed a preliminary agreement to acquire 100 percent of the company's shares for PLN 1.183 billion and announced the completion of the project and the start of full production in 2027.

How it went

Assessment: too early to assess, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverypartial[5]
Scheduledelayed[6]

Timeline

Slip: about 8 years vs. the original date (given as a year)

  1. Announced2015
  2. Construction start7 Jan 2020
  3. Original date2019
  4. Current date2027

Change history

  • 22 Jun 2023stage: commissioning
  • 7 Jan 2020stage: construction
  • 18 Apr 2019stage: tender
  • 2015stage: announced

Significance

One of the largest investments in the history of the Polish chemical industry, intended to expand Grupa Azoty's activities into plastics production (437 thousand tonnes of polypropylene per year). Part of the complex is its own gas terminal in Police, enabling maritime imports of propane and ethylene. The cost escalation from approximately PLN 1.7 billion (2015) to over PLN 7.2 billion, together with the failed attempts to reach full operation, drove the special-purpose company into restructuring and the takeover of the project by Orlen – the project became one of the leading Polish examples of a megaproject in financial trouble despite the technical completion of construction.

Sources 9 · 3 independent · 9 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Grupa Azoty22 Jun 2023
    CostConstruction startStage history
    CostBudżet projektu Polimery Police to ponad 7,2 mld zł
    Construction startprzekazanie placu budowy Generalnemu Wykonawcy nastąpiło 7 stycznia 2020 roku.
    Stage historyZgodnie z harmonogramem inwestycji, rozpoczęcie produkcji polipropylenu następuje
  2. Grupa Azoty18 Apr 2019
    Stage history
    Stage historyZarząd PDH Polska S.A. (PDH) 18 kwietnia 2019 r. podjął uchwałę w sprawie definitywnego wyboru oferenta – Hyundai Engineering Co., Ltd.
  3. Grupa Azoty1 Apr 2026
    Investor
    InvestorGrupa Azoty zawarła z Orlenem przedwstępną umowę sprzedaży akcji Grupy Azoty Polyolefins
  4. WNP.PL1 Apr 2026
  5. WNP.PL1 Apr 2026
    StatusCurrent dateDelivery
    Status · DeliveryPróby uruchomienia produkcji podejmowane, natomiast one nigdy nie skończyły się pełnym sukcesem
    StatusOrlen przejmie 100 proc. udziałów w Polimery Police w formule cash-free, debt-free, płacąc ponad 1,18 mld zł
    Current dateGrupa Azoty Polyolefins rozpocznie produkcję w 2027 r.
  6. Energetyka2430 Dec 2025
    StageAnnouncedOriginal dateSchedule
    StageDo października 2024 r. instalacja wyprodukowała 200 tys. ton polipropylenu
    AnnouncedHistoria projektu Polimery Police sięga wiosny 2015 r., kiedy to ówczesny zarząd Grupy Azoty podjął decyzję o budowie
    Original dateMiała być gotowa w 2019 r.
    SchedulePo zmianach budowa miała być skończona latem 2023 r., ale notowała opóźnienia.
  7. Grupa Azoty Polyolefins
    Locationul. Kuźnicka 1 72-010 Police; Polska
  8. Funding
    FundingPo realizacji przez partnerów wszystkich wynikających z podpisanej umowy wpłat, kapitał spółki Grupa Azoty Polyolefins wzrośnie do ok. 1,7 mld zł.