pl.ID - the Polish ID Card (electronic identity document)
pl.ID was a flagship e-government project carried out under the 7th priority axis of the Innovative Economy Operational Programme (POIG) in the 2007-2013 financial perspective. In 2008-2009 the then Ministry of Internal Affairs and Administration and the Ministry of Regional Development signed an agreement to carry out the undertaking, whose total budget stood at PLN 511 million, of which PLN 370 million was to be spent on rolling out a multifunctional electronic identity document with an authentication feature. The project envisaged the integration of state registers and the issuing of an identity card with an electronic layer (chip). Rollout of the card with the electronic layer was repeatedly delayed, and the project acquired "non-functioning" status, which created a risk of having to repay around PLN 148 million to the European Commission (85 per cent of the eligible costs incurred). The scope of the undertaking was modified to focus on building the System Rejestrów Państwowych (State Registers System, SRP), which was launched on 1 March 2015. The electronic-document component was continued as the e-Dowód (e-ID card), issued from March 2019.
Rollout of the multifunctional electronic identity document under pl.ID was repeatedly delayed, and the project acquired "non-functioning" status; a real threat emerged that Poland would have to repay 85 per cent of the eligible costs incurred, i.e. around PLN 148 million. The scope of the undertaking was modified to focus on the System Rejestrów Państwowych (launched on 1 March 2015), whose operation, according to a Supreme Audit Office (NIK) inspection, involved numerous problems, mainly shortcomings in the functionality of the Źródło application. The document with the electronic layer was ultimately continued as the e-Dowód (issued from March 2019).
How it went
Assessment: settled, as of 2019. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section
- Current
- SRP uruchomiony 2015; e-Dowód wydawany od marca 2019 r.
Timeline
- Construction start2008
- Delivery2019
Change history
- 2019status: completedProjekt pl.ID został zrestrukturyzowany i dostarczony: uruchomił System Rejestrów Państwowych (2015), a element dowodu z warstwą elektroniczną dokończono jako e-Dowód (wydawanie od marca 2019 r.). e-Dowód jest kontynuacją programu, nie odrębnym projektem w rejestrze.
Significance
pl.ID was one of the key projects for the computerisation of the state in the 2007-2013 perspective and the starting point for two lasting outcomes: the System Rejestrów Państwowych (SRP), launched on 1 March 2015 and integrating, among others, the PESEL register, the identity-card register and the civil-status register, and the identity card with an electronic layer (e-Dowód), whose issuance began in March 2019. The project's history, marked by years of delay in rolling out the electronic document, a "non-functioning" project status, and the risk of having to repay around PLN 148 million to the European Commission, became one of the most frequently cited examples of the difficulties facing large e-government projects in Poland.
Sources 7 · 5 independent · 7 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- [1]Po ośmiu latach polski e-dowód znalazł się na ostatniej prostej. Potknięcie byłoby bardzo kosztowne ↗archived ✓Spider's WebMar 2018CostInvestorFailure descriptionSchedule
CostŁączny budżet opiewał na 511 mln zł.
InvestorW latach 2008–2009 ówczesne Ministerstwa Spraw Wewnętrznych i Administracji oraz Rozwoju Regionalnego zawarły porozumienie
Failure descriptionWtedy pierwszy raz pojawiła się realna groźba, że Polska będzie musiała oddać 85 proc. poniesionych kosztów kwalifikowanych, czyli ok. 148 mln zł.
ScheduleDwa lata później ówczesny Komitet Rady Ministrów ds. cyfryzacji, na wniosek Ministerstwa Spraw Wewnętrznych, rekomendował przesunięcie terminu wdrożenia elektronicznej warstwy dowodu osobistego.
- Ministerstwo Cyfryzacji (gov.pl)2019
- Najwyższa Izba Kontroli22 Mar 2017P/16/006/KAPUtilisation
UtilisationPomimo 2-miesięcznego opóźnienia w uruchomieniu Systemu oraz licznych problemów z aplikacją „Źródło” w urzędach stanu cywilnego, udostępnienie Systemu Rejestrów Państwowych umożliwiło obywatelom załatwianie spraw w zakresie wydawania dowodów osobistych oraz aktów stanu cywilnego (dotyczących urodzenia, małżeństwa, zgonu) w dowolnym urzędzie gminy, niezależnie od miejsca zamieszkania.
- Ministerstwo Cyfryzacji (gov.pl)Scope
ScopeKoncepcja e-Dowodu – kontynuacja projektu pl.ID i realizacja powiązanych projektów
- Prawo.pl4 Mar 2020StatusStageDelivery
Status · StagePrawie trzy miliony Polaków odebrało już swój dowód z warstwą elektroniczną.
DeliveryDowód z warstwą elektroniczną działa już od roku
- FundingConstruction start
Funding · Construction startRealizacja projektu e-dowód to kontynuacja nieudanego projektu pl.ID zapoczątkowanego w 2008 r., którego niezakończenie w terminie groziło koniecznością zwrotu do Unii Europejskiej kwoty blisko 150 milionów złotych.
- Funding
Fundingwszystkie wydatki związane z ich realizacją po tym terminie będą musiały zostać sfinansowane z budżetu państwa