National Teleinformatics Network for Emergency Number 112 (OST 112)

completedstage: operationaldelivered
PLN 149 million
contract value · data from 2012incl. VAT≈ PLN 149 million (value-by-stage, est., nominal)planned funding: EU funds, state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

OST 112 is a dedicated, nationwide teleinformatics network built to handle the 112 emergency number, independent of commercial operators. The beneficiary and investor of the project was the MSWiA Information Technology Projects Centre (Centrum Projektów Informatycznych MSWiA), and the network was co-financed under the Operational Programme Innovative Economy (7th priority axis, "Information Society: Building Electronic Administration"). The total planned project budget was PLN 165 million, of which 85% (PLN 140,250,000) was co-financing from POIG and 15% (PLN 24,750,000) was the beneficiary's own contribution. In the tender procedure for the construction and deployment of the network, concluded on 28 December 2009, the offer of the company ATM SA was selected as the most advantageous; ATM designed and built the network based on the transmission links of Telekomunikacja Polska and Exatel. The implementation works, lasting almost twenty-seven months, were completed in 2012 (announcement of the network's readiness: 9 May 2012). The total value of the contracted works related to building the network (excluding the provision of telecommunications services) was approximately PLN 149 million gross. OST 112 covered the infrastructure of more than 900 locations important for the functioning of the Emergency Notification System, including Police headquarters, State Fire Service units, and voivodeship emergency notification centres. In later years, Exatel became the operator and contractor for the network's expansion (a 2017 contract worth almost PLN 200 million, building more than 1,000 km of new fibre-optic lines); the network, described as the state's largest fibre-optic network, today also serves the National Registers System and the Central Vehicle and Driver Register (CEPiK). This record concerns the original 2009-2012 build (beneficiary: CPI MSWiA, contractor: ATM, financing: POIG), not the later Exatel operating contract.

How it went

Assessment: settled, as of 9 May 2012. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[1]
Utilisationin use[4]
obsługa krytycznych systemów państwa
Current
sieć obsługuje numer alarmowy 112 oraz (w latach późniejszych) System Rejestrów Państwowych i CEPiK; obejmuje ponad 900 lokalizacji (2017)

Timeline

  1. Announced2009
  2. Original dateDec 2011
  3. Delivery9 May 2012

Change history

  • 9 May 2012stage: operational
  • 28 Dec 2009stage: tender

Significance

OST 112 was the state's first dedicated, nationwide teleinformatics network, built specifically to handle the 112 emergency number, independent of commercial operators' networks and linking more than 900 key locations of the Emergency Notification System (Police, State Fire Service, voivodeship emergency notification centres). It created a secure, state-owned transmission backbone which in later years became the foundation for the operation of further critical government systems: the National Registers System and the Central Vehicle and Driver Register (CEPiK). The network is described as the state's largest fibre-optic network and one of the largest telecommunications projects carried out for the purposes of security and public administration in Poland.

Sources 5 · 5 independent · 1 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Rzeczpospolita (rp.pl)9 May 2012
    StatusStageCostDelivery
    Status · DeliveryFirma ATM zakończyła prace wdrożeniowe ogólnopolskiej sieci teleinformatycznej
    StageATM zaprojektowała i zbudowała sieć OST 112
    CostSumaryczna wartość zakontraktowanych prac związanych z budową sieci bez świadczenia usług telekomunikacyjnych wyniosła ok. 149 mln zł brutto
    DeliveryPrace trwały blisko dwadzieścia siedem miesięcy
  2. Powiat Goleniowski
    Original dateFunding
    Original dateProjekt OST 112 ma się zakończyć w grudniu 2011 roku.
    FundingDofinansowaniu z Programu Operacyjnego Innowacyjna Gospodarka w ramach 7. osi priorytetowej „Społeczeństwo informacyjne - budowa elektronicznej administracji” podlega 85% wartości projektu, czyli 140 250 000 zł.
    Funding26 czerwca między Ministerstwem Spraw Wewnętrznych i Administracji oraz Ministerstwem Rozwoju Regionalnego została zawarta umowa o dofinansowanie.
    FundingPozostałe 15%, tj. 24 750 000 zł stanowi wkład własny Beneficjenta.
  3. Rynek Zdrowia
    AnnouncedInvestor
    Announcedw postępowaniu przetargowym na Budowę i wdrożenie ogólnopolskiej sieci teleinformatycznej na potrzeby obsługi numeru alarmowego nr 112 jako najkorzystniejszą wybrano ofertę złożoną przez ATM SA
    InvestorCentrum Projektów Informatycznych MSWiA
  4. Exatel S.A.2017
    Utilisation
    UtilisationZ infrastruktury OST 112 korzystają najważniejsze systemy odpowiadające za bezpieczeństwo Polaków, m.in. numer alarmowy 112, System Rejestrów Państwowych (zawiera kluczowe dane polskich obywateli) czy Centralna Ewidencja Pojazdów i Kierowców (CEPiK). Do sieci jest podpiętych kilka tysięcy lokalizacji w całej Polsce.
  5. BiznesAlert5 Oct 2017