🖥Digitalstrategic

National Educational Network (OSE)

operating, being expandedstage: operationaldelivered
PLN 320 million
programme budget (multi-year) · data from 2017net or gross: not recorded≈ PLN 320 million (value-by-stage, est., nominal)planned funding: EU funds, state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The National Educational Network (OSE) is a government programme for a public telecommunications network giving schools throughout Poland the opportunity to connect to fast, free, and secure internet. Its legal basis is the Act of 27 October 2017 on the National Educational Network (Journal of Laws 2017, item 2184). NASK National Research Institute was designated as the OSE operator. The programme provides for connecting approximately 30,000 schools at 19,500 locations. The implementation model provided for the first schools to be able to use OSE services from 1 September 2018, with all 19,500 locations to be connected by 2020. The cost of implementing OSE was estimated at PLN 320 million (financed from the Digital Poland Operational Programme), while the cost of operation (purchasing telecommunications services providing schools with free internet access) was estimated at more than PLN 1.3 billion over a 10-year horizon, financed from the state budget.

How it went

Assessment: provisional, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[6]
Utilisationin use[6]
szkoły objęte siecią OSE
Current
ponad 19 tys. szkół objętych siecią OSE; sieci dostępowe wybudowane lub zmodernizowane w ponad 20 tys. szkół (2020)
Capacity or target
ok. 30 tys. szkół w 19 500 lokalizacjach (wartość docelowa)
Unit
szkoły

Timeline

  1. Announced27 Oct 2017
  2. Original date2020

Significance

OSE is one of the largest national digitalisation projects: a public telecommunications network built to provide almost all schools in Poland (approximately 30,000 institutions at 19,500 locations) with fast, free, and secure internet access at a bandwidth of 100 Mbit/s. The programme, run by NASK under a dedicated act, narrowed the gap in broadband internet access between urban and rural schools and created a nationwide infrastructure supporting digital education.

Sources 6 · 4 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. NASK / OSE
  2. Wikipedia (pl)
    Original date
    Original dateRok 2020 – przyłączenie wszystkich 19 500 lokalizacji
  3. gov.pl / Ministerstwo Cyfryzacji
    StatusStageCostInvestorFunding
    StatusStatus projektu Realizowany
    Stagemodel wdrożenia OSE zakłada umożliwienie korzystania z jej usług pierwszym szkołom od 1 września 2018 r.
    CostKoszty wdrożenia OSE szacowane są na 320 mln zł
    InvestorSieć ta będzie operowana przez Operatora OSE, którym został NASK
    FundingKoszty wdrożenia OSE szacowane są na 320 mln zł (środki te zostaną pozyskane z Programu Operacyjnego Polska Cyfrowa)
    Fundingjej funkcjonowania (w tym zakupu usług od operatorów telekomunikacyjnych w celu świadczenia szkołom bezpłatnych usług dostępu do Internetu) - ponad 1,3 mld zł w perspektywie 10 lat (od 2022 roku ok. 164 mln zł rocznie) i zostaną sfinansowane z budżetu państwa
  4. ISAP – Internetowy System Aktów Prawnych27 Oct 2017
  5. NASK / OSE
    Announced
    AnnouncedUstawą z 27 października 2017 r. o Ogólnopolskiej Sieci Edukacyjnej
  6. Rzeczpospolita (edukacja.rp.pl)18 Feb 2026
    StatusDeliveryUtilisation
    Status · Delivery · UtilisationOgólnopolska Sieć Edukacyjna od 2018 r. zapewnia bezpłatny, szybki i bezpieczny internet we wszystkich polskich szkołach.